9/24/2018September 25, 2018 – Sarah Klinetob LoweBlower Doors for Builderswww.phrc.psu.eduPennsylvania Housing Research Center The Pennsylvania Housing Research Center serves the home buildingindustry and the residents of Pennsylvania by improving the quality andaffordability of housing. We conduct applied research, foster the development andcommercialization of innovative technologies, and transfer appropriatetechnologies to the housing community. The PHRC is housed within the Department of Civil & EnvironmentalEngineering at Penn State. For more information about the PHRC(publications, webinars, conferences), check out our website, phrc.psu.edu.2Continuing Education At end of the program, you can register for acertificate to receive the following credits for thissession:- 1.0 PA Dept L&I Contact Hour- 1.0 PDH- 1.0 AIA LU HSW (PHRCWEB916)Provider # 60114115PPP ID: 15623- 1.0 ICC Contact Hour (0.1 CEU) (8970)- 1.0 NARI hour/CEU1

9/24/2018September 25, 2018 – Sarah Klinetob LoweBlower Doors for Builderswww.phrc.psu.eduAIA InfoCredit(s) earned on completion ofthis course will be reported to AIACES for AIA members. Certificatesof Completion for both AIAmembers and non-AIA membersare available upon request.CES for continuing professionaleducation. As such, it does notinclude content that may bedeemed or construed to be anapproval or endorsement by the AIAof any material of construction orany method or manner ofhandling, using, distributing, ordealing in any material or product.Questions related to specific materials, methods,and services will be addressed at the conclusion ofthis presentation.This course is registered with AIA5Description Beyond visual inspection, Section R402.4.1.2 of the 2015IECC now requires testing and verification of the building’sair leakage rate to meet the mandatory 5 air changes perhour at 50 Pascals (5 ACH50) or less in Pennsylvania. Tomeet this requirement builders must have a third partyapproved by their local code jurisdiction complete a blowerdoor test and submit the air leakage results to the codeofficial. This webinar will provide an overview of the generallogistics of completing a blower door test for typicalresidential construction projects to assist builders inscheduling and planning for this mandatory requirement.62

9/24/2018Learning Objectives Understand the general process and setup of a blower doortest to ensure proper building ventilation and indoor airquality Describe how to prepare a construction site before and whilea blower door test is being performed for overall site safety Analyze appropriate times in the construction schedule forscheduling and completing a blower door test Identify resources and next steps if a home does not meetthe required 5 ACH50 to ensure building energy efficiency7Poll Time!Rate your experience with blower door tests.Blower WHAT?Yeah, I’ve heard of that.We’re getting there.8Little to no knowledge or experience with blower door tests.Know what blower door tests are BUT have not run one on your homes.Know what blower door tests are AND have run one or more blowerdoor test on your homes.We got this.Know what blower door tests are AND run them semi-regularly onyour homes.Turn the screen over to me,I could teach this webinar.Know what blower door tests are AND run them on all your homes.Webinar Overview Getting You PreparedYourCompany- What The Code Says- Basics of Air Tightness- Basics of Blower Door TestsYour Site Getting Your Site Prepared- Scheduling- Site PreparationYou Getting Your Company Prepared9- Test current homes3

9/24/20182015 IECC Section R402.4.1.22015 IRC Section N1102.4.1.2 Topic: Air leakage testing Code Section Summary: 2015IECC mandates air leakagetesting and the rate to notexceed 3ACH50 in climatezones 3-8 PA Amendment: Changes therequirement to not exceed5ACH50 in climate zones 1-8Source: International Code Council. (2014). 2015 International Energy Conservation Code, ICC Country Club Hill, Ill.10Section R402.4.1.2 TestingOld Code Provision (2009 IECC) New PA Code ProvisionAIR LEAKAGEREQUIREMENT 7 Air Changes Per Hour@ 50 Pascals (ACH50) 5 ACH50VERIFICATIONREQUIREMENTBlower door test OR through visualbuilding envelope inspection.Blower door test (“Test in accordance with ASTM E779 or ASTM E 1827”) that is:1) performed at any time after creation of allpenetrations of the building thermal envelope2) conducted by an approved third partyCode official visual inspectionWritten report that is signed by the partyconducting the test and given to the code officialREPORTINGMETHOD11Section R402.4.1.2 TestingOld CodeProvision(2009 IECC)New PA Code Provision1.2.TESTCONDITIONS(Same if doing ablower door test)3.4.5.6.Exterior windows and doors, fireplace and stove doors shall be closed, but notsealed, beyond the intended weatherstripping or other infiltration control measures.Dampers including exhaust, intake, makeup air, backdraft and flue dampers shallbe closed, but not sealed beyond intended infiltration control measures.Interior doors, if installed at the time of the test, shall be open.Exterior doors for continuous ventilation systems and heat recovery ventilators shallbe closed and sealed.Heating and cooling systems, if installed at the time of the test, shall be turned off.Supply and return registers, if installed at the time of the test, shall be fully open.124

9/24/2018Basics of Airtightness: Why Airseal?1.2.3.4.Lower heating billsHigher comfort / fewer draftsBetter performing mechanical ventilation systemReduce moisture movement in the envelope / reducepotential for mold and rot5. Potentially smaller heating/cooling equipment sizes13Basics of Airtightness: Where and cuments/BECP 20Leakage%20Guide Sept2011 v00 lores.pdf14Airtightness Requirement: 5 ACH50 Measured in Air Changes Per Hour at 50 Pascals(ACH50 / ACH50) 50 pascals – equivalent to 20 MPH wind onthe houseValue we need(Air Changes PerHour @ 50 Pascals)Value from the blowerdoor pressure gauge Constant(60 minutes(Cubic Feet PerMinute @ 50 Pascals) per hour)ACH50 lite-a-lair/CFM50 x 60V 5Volume ofthe House(Cubic Feet)5

9/24/2018Air Sealing for 5 ACH50 Strategies? Tuesday, November 13 @ 1pm: PHRC Webinar!Air Sealing for 5 ACH50DescriptionPennsylvania’s prescriptive air leakage requirements have recently beenchanged from 7 ACH50 to 5 ACH50. With this change, builders may have tomodify their air sealing package to comply with the prescriptive airinfiltration requirements. In this webinar we will look at areas of concern forair leakage and review several techniques to potential seal those areas.Learning trometrie/permeabilite-a-lair/Review the 2015 IRC and IECC requirements on air leakage.Understand the physical transition of a home with a higher leakage rateto a home with a lower leakage rate and how that change can affect thesustainability of building componentsLearn why air sealing is important to the occupant comfort and healthby not allowing air infiltration from potentially contaminated areasReview air sealing techniques that can help achieve this lowerprescriptive standard.Webinar Overview Getting You Prepared What The Code Says Basics of Air Tightness- Basics of Blower Door TestsYourCompanyYour Site Getting Your Site Prepared- Scheduling- Site PreparationYou Getting Your Company Prepared- Test current homes17Blower Door SetupSet up on an exterior doorAdjustable frame & cover forany size single exterior doorAir pressure gaugeDoorTestBlower (Fan)Fan with adjustable rings fornearly all SF buildingsFan power cord(standard ments-Loans6

9/24/2018Blower Door: Fan Sizes (Single om/mini-fan-blower-door-system-with-dg-1000/Blower Door: Fan Sizes (Multifamily)20Blower Door: Fan Sizes (Multifamily)217

9/24/2018Blower Door: Test /dg10-kit-001.htmBlower Door Test: ichmond-virginia-home-save-moneyBlower Door Test: MeasurementsACH50 Example #1:2,500 ft2 house with 8’ ceilingsACH50 ACH50 CFM50 X 60Vft3𝟐𝟏𝟕𝟓 min(𝟐𝟓𝟎𝟎 𝐟𝐭𝟐 𝐱 𝟖 𝐟𝐭)ACH50 𝟔. 𝟓24minX 𝟔𝟎 hourCFM50 X 60VExample #2:3,500 ft 2 house with 9’ ceilingsACH50 CFM50 X 60Vft3ACH50 min𝟐𝟏𝟕𝟓 min X 𝟔𝟎 hour(𝟑𝟓𝟎𝟎 𝐟𝐭𝟐 𝐱 𝟗 𝐟𝐭)ACH50 𝟒. 𝟏CFM50 2175𝐴𝑝𝑝𝑟𝑜𝑥. 𝐻𝑜𝑙𝑒 𝑆𝑖𝑧𝑒 1,0001,000 2.175 a-home-save-money8

9/24/2018Webinar Overview Getting You PreparedYourCompany What The Code Says Basics of Air Tightness Basics of Blower Door TestsYour Site Getting Your Site Prepared- Scheduling- Site PreparationYou Getting Your Company Prepared- Test current homes25Code RequirementsNew PA Code ProvisionAIR LEAKAGEREQUIREMENT 5 ACH50VERIFICATIONREQUIREMENTBlower door test (“Test in accordance with ASTM E 779 or ASTM E 1827”) that is:1) performed at any time after creation of all penetrations of the building thermal envelope2) conducted by an approved third partyTESTCONDITIONS261. Exterior windows and doors, fireplace and stove doors shall be closed, but not sealed,beyond the intended weatherstripping or other infiltration control measures.2. Dampers including exhaust, intake, makeup air, backdraft and flue dampers shall beclosed, but not sealed beyond intended infiltration control measures.3. Interior doors, if installed at the time of the test, shall be open.4. Exterior doors for continuous ventilation systems and heat recovery ventilators shall beclosed and sealed.5. Heating and cooling systems, if installed at the time of the test, shall be turned off.6. Supply and return registers, if installed at the time of the test, shall be fully open.Approved Third Party Will depend on your code enforcement office No specific “blower door certification” Certifications that include blower door operationinclude:- Building Performance Institute (BPI)- RESNET HERS Rater- Passive House Verifiers279

9/24/2018Scheduling!1) Call your code office for ApprovedThird Parties2) Call an Approved Third Party- Get on their list- Get their prices3) Schedule the Test Date- After all exterior penetrations are completed- At a time with no other interior sub ks-happen-at-the-surface-not-in-the-volu meScheduling!Contact Code Office /Approved Third PartyScheduleTest DateTest Date29Talk Overview Getting You PreparedYourCompany What The Code Says Basics of Air Tightness Basics of Blower Door TestsYour Site Getting Your Site Prepared Scheduling Site PreparationYou Getting Your Company Prepared30- Test current homes10

9/24/20181) Do A Blower Door Test After Rough-In /As Early as You -blower-door-test/img frared/1a) Use a smoke pen during the ell-instrument-company-smoke-pen.html1b) Infrared During a Blower Door TestBOTTOM t/uploads/2014/05/EVAP.jpgATTIC s/2014/05/MAnhole.jpg3311

9/24/2018Blower Door Test Video34https://www.youtube.com/watch?v icZG05XU9pM2) Test Multiple Home SizesACH50 CFM50 X 60VExample #2:3,500 ft 2 house with 9’ ceilingsExample #1:2,500 ft2 house with 8’ ceilingsACH50 CFM50 X 60ftACH50 ACH50 V3ft3min𝟐𝟏𝟕𝟓 min X 𝟔𝟎 hourACH50 (𝟐𝟓𝟎𝟎 𝐟𝐭𝟐 𝐱 𝟖 𝐟𝐭)35min𝟐𝟏𝟕𝟓 min X 𝟔𝟎 hour(𝟑𝟓𝟎𝟎 𝐟𝐭𝟐 𝐱 𝟗 𝐟𝐭)ACH50 𝟒. 𝟏ACH50 𝟔. 𝟓𝐴𝑝𝑝𝑟𝑜𝑥. 𝐻𝑜𝑙𝑒 𝑆𝑖𝑧𝑒 CFM50 X 60VCFM501,000 21751,000 2.175 a-home-save-moneyUnknowns Who will be considered an “approved” third party Testing additions for air ry/modular-home-additions/12

9/24/2018Webinar Overview Getting You PreparedYourCompany What The Code Says Basics of Air Tightness Basics of Blower Door TestsYour Site Getting Your Site Prepared Scheduling Site PreparationYou Getting Your Company Prepared Test Current Homes37Questions?www.phrc.psu.edu38Blower Doors for Builderswww.phrc.psu.edu13

Know what blower door tests are AND have run one or more blower door test on your homes. We got this. Know what blower door tests are AND run them semi-regularly on your homes. Turn the screen over to me, I could teach this webinar. Know what blower door tests are AND run them on all your homes. Webinar Overview 9 Getting You Prepared