Front coverLenovo UPS QuickReference GuideFeatures a "cheat sheet" aboutLenovo’s current UninterruptiblePower Supply productsProvides a summary of keyspecifications of the UPS unitsIncludes a reference of availableline cords with illustrations of theconnectorsIncludes links to other power- andcooling-related resourcesRani DoughtyDavid WattsClick here to check for updates

AbstractThis quick reference guide describes all Lenovo uninterruptible power supply (UPS) offerings.This guide helps determine the best fit UPS for your needs by providing key technicalspecifications of each UPS offering, including specifications of the input and output power foreach UPS and number and type of outlets.A quick reference look-up table for line cord options also is provided for each UPS along withan illustration of each line cord’s respective plug.At Lenovo Press, we bring together experts to produce technical publications around topics ofimportance to you, providing information and best practices for using Lenovo products andsolutions to solve IT challenges.For more information about our most recent publications, see this website:http://lenovopress.comContentsLenovo UPS offerings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3Line cord options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5Optional Accessories . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9Installation and user’s manuals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9Lenovo Press product guides. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9Power and cooling support. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10Abbreviations and acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10Change history . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11Authors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11Notices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12Trademarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 132Lenovo UPS Quick Reference Guide

Lenovo UPS offeringsTable 1 shows all of the available UPS offerings from Lenovo and their technicalspecifications.Table 1 Lenovo UPS offeringsUPSRackheightInput:Voltage /Phase /Max Amps /FrequencyOutput:Voltage (V) /Apparent Power (VA) /Wattage (W) /Amperage (A)OutletsLine CordT1kVA Tower UPS(100 - 125 VAC)55951AXToweronly100 - 125 VAC1 phase8.8 A50/60 Hz100 VAC / 833 VA / 641 W / 8.4 A120 VAC / 1000 VA / 770 W / 8.4 A125 VAC / 1000 VA / 770 W / 8.4 A8x 5-15RFixed 1.8 m(6 ft) NEMA 5-15PT1kVA Tower UPS(200 - 240 VAC)55951KXToweronly200 - 240 VAC1 phase5.3 A50/60 Hz200 VAC / 1035 VA / 693 W / 5.2 A208 VAC / 1035 VA / 693 W / 5.2 A220 VAC / 1150 VA / 770 W / 5.3 A230 VAC / 1150 VA / 770 W / 5.3 A240 VAC / 1150 VA / 770 W / 5.3 A8x C13For moreinformation, seeTable 2 on page 5T1.5kVA Tower UPS(100 - 125 VAC)55952AXToweronly100 - 125 VAC1 phase12 A50/6 0Hz100 VAC / 1080 VA / 825 W / 10.8 A120 VAC / 1440 VA / 1100 W / 12 A125 VAC / 1440 VA / 1100 W / 12 A8x 5-15RFixed 1.8m(6ft) NEMA 5-15PT1.5kVA Tower UPS(200 - 240 VAC)55952KXToweronly200 - 240 VAC1 phase7.1 A50/60 Hz200 VAC / 1395 VA / 990 W / 7 A208 VAC / 1395 VA / 990 W / 7 A220 VAC / 1550 VA / 1100 W / 7.1 A230 VAC / 1550 VA / 1100 W / 7.1 A240 VAC / 1550 VA / 1100 W / 7.1 A8x C13For moreinformation, seeTable 2 on page 5RT1.5kVA 2U Rackor Tower UPS(100 - 125 VAC)55941AX2U100 - 125 VAC1 phase12 A50/60 Hz100 VAC / 1200 VA / 1200 W / 12.0 A120 VAC / 1440 VA / 1440 W / 12.0 A125 VAC / 1440 VA / 1440 W / 11.5 A8x 5-15RFixed2.5 m (8 ft)NEMA 5-15PRT1.5kVA 2U Rackor Tower UPS(200 - 240 VAC)55941KX2U200 - 240 VAC1 phase10 A50/60 Hz200 VAC / 1550 VA / 1100 W / 7.5 A208 VAC / 1550 VA / 1100 W / 7.3 A220 VAC / 1550 VA / 1100 W / 6.9 A230 VAC / 1550 VA / 1100 W / 6.6 A240 VAC / 1550 VA / 1100 W / 6.3 A8x C13For moreinformation, seeTable 3 on page 6RT2.2kVA 2U Rackor Tower UPS(100 - 125 VAC)55942AX2U100 - 125 VAC1 phase16A50/60 Hz100 VAC / 1330 VA / 1300 W / 13.3 A120 VAC / 1920 VA / 1920 W / 16.0 A125 VAC / 1920 VA / 1920 W / 15.6 A8x 5-20RFixed2.5 m (8 ft)NEMA 5-20PRT2.2kVA 2U Rackor Tower UPS(200 - 240 VAC)55942KX2U200 - 240 VAC1 phase16 A50/60 Hz200 VAC / 1700 VA / 1530 W / 8.5 A208 VAC / 1980 VA / 1780 W / 9.5 A220 VAC / 2200 VA / 1980 W / 10.0 A230 VAC / 2200 VA / 1980 W / 9.6 A240 VAC / 2200 VA / 1980 W / 9.2 A8x C13For moreinformation, seeTable 4 on page 7Rack EBM1.5K/2.2K55942BX2U---- Copyright Lenovo 2015. All rights reserved.3

UPSRackheightInput:Voltage /Phase /Max Amps /FrequencyOutput:Voltage (V) /Apparent Power (VA) /Wattage (W) /Amperage (A)OutletsLine CordRT3kVA 2U Rack orTower UPS(100 - 125 VAC)55943AX2U100 - 125 VAC1 phase24 A50/60 Hz100 VAC / 2400 VA / 2160 W / 24.0 A120 VAC / 3000 VA / 2700 W / 25.0 A125 VAC / 3000 VA / 2700 W / 24.0 A6x 5-20RFixed2.5 m (8 ft)NEMA L5-30PRT3kVA 2U Rack orTower UPS(200 - 240 VAC)55943KX2U200 - 240 VAC1 phase16 A50/60 Hz200 VAC / 2700 VA / 2430 W / 13.5 A208 VAC / 3000 VA / 2700 W / 14.5 A220 VAC / 3000 VA / 2700 W / 13.7 A230 VAC / 3000 VA / 2700 W / 13.0 A240 VAC / 3000 VA / 2700 W / 12.5 A8x C131x C19For moreinformation, seeTable 4 on page 73K Rack EBM55943BX2U----RT5kVA 3U Rack orTower UPS(200 - 240 VAC)55945KX3U200 - 240 VAC1 phase25 A50/60 Hz200 VAC / 5000 VA / 4500 W / 25.0 A208 VAC / 5000 VA / 4500 W /24.0 A220 VAC / 5000 VA / 4500 W / 22.7 A230 VAC / 5000 VA / 4500 W / 21.7 A240 VAC / 5000 VA / 4500 W / 20.8 A8x C132x C19For moreinformation, seeTable 5 on page 8RT6kVA 3U Rack orTower UPS(200 - 240 VAC)55946KX3U200 - 240 VAC1 phase30 A50/60 Hz200 VAC / 6000 VA / 5400 W / 30.0 A208 VAC / 6000 VA / 5400 W / 28.8 A220 VAC / 6000 VA / 5400 W / 27.3 A230 VAC / 6000 VA / 5400 W / 26.1 A240 VAC / 6000 VA / 5400 W / 25.0 A8x C132x C191xhardwiredoutputHardwired to PDU5K/6K Rack EBM55946BX3U----RT8kVA 6U Rack orTower UPS(200 - 240 VAC)55948KX6U200 - 240 VAC1 phase40 A50/60 Hz4x C191xhardwireoutputRT8kVA 6U 3:1Phase Rack orTower UPS(380 - 415 VAC)55948PX6U380 - 415 VAC3 phase Y13.3 A50/60 Hz200 VAC / 8000 VA / 7200 W / 40.0 A208 VAC / 8000 VA / 7200 W / 38.5 A220 VAC / 8000 VA / 7200 W / 36.4 A230 VAC / 8000 VA / 7200 W / 34.8 A240 VAC / 8000 VA /7200 W / 33.3 A250 VAC / 8000 VA / 7200 W / 32.0 ART11kVA 6U Rackor Tower UPS(200 - 240 VAC)55949KX6U200 - 240 VAC1 phase50 A50/60 Hz4x C191xhardwireoutputRT11kVA 6U 3:1Phase Rack orTower UPS(380 - 415 VAC)55949PX6U380 - 415 VAC3 phase Y16.7 A50/60 Hz200 VAC / 10000 VA / 9000 W / 50.0 A208 VAC / 10000 VA / 9000 W / 48.1 A220 VAC / 11000 VA / 9900 W / 50.0 A230 VAC / 11000 VA / 10000 W / 47.8 A240 VAC / 11000 VA / 10000 W / 45.8 A250 VAC / 10000 VA / 9000 W / 40.0 ARack EBM8K/11K55949BX3U-4x C191xhardwireoutputHardwired to PDU4Lenovo UPS Quick Reference Guide-4x C191xhardwireoutput--

Line cord optionsLine cord options for the following UPS units are described in this section: “Lenovo UPS1000VA and UPS1500VA Tower”“Lenovo UPS1500VA Rack” on page 6“Lenovo UPS2200VA and UPS3000VA Rack” on page 7“Lenovo UPS5000VA Rack” on page 8Lenovo UPS1000VA and UPS1500VA TowerTable 2 lists the country-specific line cord options that are available for the T1kVA Tower UPS(200 - 240 VAC) 55951KX and the T1.5kVA Tower UPS (200 - 240 VAC) 55952KX.Table 2 UPS1000VA and UPS1500VA Line Cord OptionsLine Cord DescriptionPartnumberFeaturecode2.8m (9ft) – 10A/240V C13 to NEMA 6-15P – USA/Canada46M2592A1RF2.8m (9ft) – 10A C13 to IRAM 2063 – Argentina39Y793062222.8m (9ft) – 10A C13 to AS/NZS 3112 – Australia/NZ39Y792462112.8m (9ft) – 10A C13 to NBR 6147 – Brazil39Y792962232.8m (9ft) – 6A C13 to GB 2099.1 – China39Y792862102.8m (9ft) – 10A C13 to DK 2-5A – Denmark39Y791862132.8m (9ft) – 10A C13 to CEE 7/7 – Europe39Y791762122.8m (9ft) – 10A C13 to IS6538 – India39Y792762692.8m (9ft) – 10A C13 to SI 32 – Israel39Y792062182.8m (9ft) – 10A C13 to CEE 7/7 – Italy39Y792162172.8m (9ft) – 7A C13 to KETI 15A/250V – South Korea39Y79256219From C13 to5

Line Cord DescriptionPartnumberFeaturecode2.8m (9ft) – 10A C13 to SABS 164/1 – South Africa39Y792262142.8m (9ft) – 10A C13 to SEV 1011 – Switzerland39Y791962162.8m (9ft) – 10A/240V C13/CNS 10917 – Taiwan81Y2375A0RF2.8m (9ft) – 10A C13 to BS 1363 – United Kingdom39Y79236215From C13 toLenovo UPS1500VA RackTable 3 lists the country-specific line cord options that are available for the RT1.5kVA 2U Rackor Tower UPS (200 - 240 VAC) 55941KX.Table 3 UPS1500VA Line Cord Options6Line Cord DescriptionPart numberFeature code4.3m (14ft) – 10A/250V C13 to IRAM 2073 Argentina81Y238464924.3m (14ft) – 10A C13 to AS/NZS 3112 – Australia/NZ81Y238365744.3m (14ft) – 10A C13 to NBR 14136 – Brazil81Y238764044.3m (14ft) – 10A C13 to GB2099.1 – China81Y237865804.3m (14ft) – 10A C13 to SB107-2-DI – Denmark81Y238265754.3m (14ft) – 10A C13 to CEE 7/7 – Europe81Y237665724.3m (14ft) – 10A C13 to IS 6538 – India81Y238665674.3m (14ft) – 10A C13 to SI 32 – Israel81Y238165794.3m (14ft) – 10A C13 to CEI 23-16 – Italy81Y23806493Lenovo UPS Quick Reference GuideFrom C13 to

Line Cord DescriptionPart numberFeature code4.3m (14ft) – 12A C13 to KSC 8305 – Korea81Y238564944.3m (14ft) – 10A C13 to SANS 164-1 – South Africa81Y237965764.3m (14ft) – 10A C13 to SEV 1011 – Switzerland81Y239065784.3m (14ft) – 10A/240V C13 to CNS 10917 – Taiwan81Y238965314.3m (14ft) – 10A C13 to BS 1363A – United Kingdom81Y23776577From C13 toLenovo UPS2200VA and UPS3000VA RackTable 4 lists the country specific-line cord options available for the RT2.2kVA 2U Rack orTower UPS (200 - 240 VAC) 55942KX and RT3kVA 2U Rack or Tower UPS (200 - 240 VAC)55943KX.Table 4 UPS2200VA and UPS3000VA Line Cord OptionsLine Cord DescriptionPart numberFeature code4.3m (14ft) – C19 to NEMA L6-20P – USA/Canada40K977262754.3m (14ft) – C19 to BS 1363/A w/13A fuse – UK40K976762784.3m (14ft) – C19 to CEE7-VII – Europe40K976662794.3m (14ft) – C19 to SABS 164 – South Africa40K977062804.3m (14ft) – C19 to CEI 23-16 – Italy40K976862814.3m (14ft) – C19 to SI 32 – Israel40K977162824.3m (14ft) – C19 to IEC 309-P N G – Denmark/Swiss40K97696283From C19 to7

Line Cord DescriptionPart numberFeature code4.3m (14ft) – C19 to AS/NZS 3112 – Australia/NZ40K977362844.3m (14ft) – C19 to IS6538 – India40K977662854.3m (14ft) – 16A/250V C19 to CNS 10917-3 – Taiwan90Y303562874.3m (14ft) – C19 to GB2099.1 – China40K977462884.3m (14ft) – 15A/250V C19 to KSC 8305 – South Korea90Y303462894.3m (14ft) – 15A/200V C19 to JIS C-8303 – Japan41Y923362914.3m (14ft) – C19 to IRAM 2073 – Argentina40K977762764.3m (14ft) – C19 to NBR 14136 – Brazil40K97756277From C19 toLenovo UPS5000VA RackTable 5 lists the country-specific line cord options available for the RT5kVA 3U Rack or TowerUPS (200 - 240 VAC) 55945KX.Table 5 UPS5000VA Line Cord Options8Line Cord DescriptionPart numberFeature code4.3m (14ft) – 30A NEMA L6-30P – USA/Canada40K961465004.3m (14ft) – 32A IEC 309 P N G – International40K961265024.3m (14ft) – 32A AUS/NZ 3112 32A – Australian/NZ40K961765054.3m (14ft) – 30A 8305 – Korean40K96186506Lenovo UPS Quick Reference GuideUTGConnector to

Optional AccessoriesAccessories for the UPS units are listed in Table 6.Table 6 Lenovo UPS accessoriesAccessoryPart numberEnvironmental Monitoring Probe (EMP)46M4113Network Management Card (NMC)a46M4110Descriptiona. The NMC is optional for 55951AX, 55951KX, 55952AX, 55952KX, 55941AX, 55941KX,55942AX, 55942KX, and 55942BX. All other UPS ship standard with the NMC.Installation and user’s manualsThe following installation and user’s manuals are available for the UPS units: Tower UPS T1.0kVA and T1.5kVA Installation and User’s isplay?lndocid MIGR-5096507 UPS RT1.5kVA, RT2.2kVA, RT3.0kVA Installation and User’s isplay?lndocid MIGR-5096504 3U UPS RT5.0kVA and RT6.0kVA Installation and User’s isplay?lndocid MIGR-5096505 6U UPS RT8.0kVA, RT11.0VA Maintenance Bypass Installation and User’s isplay?lndocid MIGR-5096506 Network Management Card Quick Installation isplay?lndocid MIGR-5087824Lenovo Press product guidesFor more information about the UPS units, see the following product guides: T1kVA and T1.5kVA Tower Uninterruptible Power Supplies, TIPS1230:http://lenovopress.com/tips1230 RT1.5kVA, RT2.2kVA and RT3kVA 2U Rack or Tower Uninterruptible Power Supplies,TIPS 1231http://lenovopress.com/tips12319

RT5kVA and RT6kVA 3U Rack or Tower Uninterruptible Power Supplies, TIPS1232:http://lenovopress.com/tips1232 RT8kVA and RT11kVA 6U Rack or Tower Uninterruptible Power Supplies, TIPS1233:http://lenovopress.com/tips1233Power and cooling supportTo calculate the power draw of your configurations, download the Power Configurator tool thatis available at this splay?lndocid LNVO-PWRCONFFor more information about power and cooling Lenovo systems, download the power andcooling guides that are available at this splay?lndocid LNVO-POWINFFor questions and support on all rack, stack and power products, use the following emailaddress:power@lenovo.comAbbreviations and acronymsThe following abbreviations and acronyms are used in this CNZSPDUSABSSANSSEVSIUPSVAVAC10Australian standardConverged Enhanced EthernetItalian Electrotechnical CommitteeChinese National StandardsExtended Battery ModuleEnvironmental Monitoring ProbeInternational Electrotechnical CommissionInstituto Argentino de Normalización y CertificaciónIndian StandardsInformation technologyJapanese Industrial StandardsKorea Electronics Technology InstituteKorean StandardsNational Electrical Manufacturers AssociationNetwork Management CardNew Zealand standardPower distribution unitSouth African Bureau of StandardsSouth African National StandardsSchweizerischen Elektrotechnischen VereinSystème International d'UnitésUninterruptible power supplyVolts AmpsVolts Alternating CurrentLenovo UPS Quick Reference Guide

Change historyChanges in the August 28, 2015 update: Added the UTG plug picture to Table 5 on page 8.AuthorsRani Doughty is a hardware specialist and data centerconsultant with a background in System x , BladeCenter ,and Flex System . She currently works with the worldwideLenovo Data Center Services (DCS) team as a developer ofthe Power Configurator. She has 12 years of technicalexperience in the x86 field. She holds an MBA and honorsdegree in IT from the University of Ballarat (Australia). Shehas written and presented worldwide extensively on IBMSystems Director, pre and post sale tools, and infrastructureplanning.David Watts is a Senior IT Consultant and the program leadfor Lenovo Press. He manages residencies and producespre-sale and post-sale technical publications for hardwareand software topics that are related to System x, ThinkServer,Flex System, and BladeCenter servers. He has authored over300 books and papers. David has worked in the IT industry,both in the U.S. and Australia, since 1989, and is currentlybased in Morrisville, North Carolina. David holds a Bachelorof Engineering degree from the University of Queensland(Australia).11

NoticesLenovo may not offer the products, services, or features discussed in this document in all countries. Consultyour local Lenovo representative for information on the products and services currently available in your area.Any reference to a Lenovo product, program, or service is not intended to state or imply that only that Lenovoproduct, program, or service may be used. Any functionally equivalent product, program, or service that doesnot infringe any Lenovo intellectual property right may be used instead. However, it is the user's responsibilityto evaluate and verify the operation of any other product, program, or service.Lenovo may have patents or pending patent applications covering subject matter described in this document.The furnishing of this document does not give you any license to these patents. You can send licenseinquiries, in writing, to:Lenovo (United States), Inc.1009 Think Place - Building OneMorrisville, NC 27560U.S.A.Attention: Lenovo Director of LicensingLENOVO PROVIDES THIS PUBLICATION “AS IS” WITHOUT WARRANTY OF ANY KIND, EITHEREXPRESS OR IMPLIED, INCLUDING, BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OFNON-INFRINGEMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Somejurisdictions do not allow disclaimer of express or implied warranties in certain transactions, therefore, thisstatement may not apply to you.This information could include technical inaccuracies or typographical errors. Changes are periodically madeto the information herein; these changes will be incorporated in new editions of the publication. Lenovo maymake improvements and/or changes in the product(s) and/or the program(s) described in this publication atany time without notice.The products described in this document are not intended for use in implantation or other life supportapplications where malfunction may result in injury or death to persons. The information contained in thisdocument does not affect or change Lenovo product specifications or warranties. Nothing in this documentshall operate as an express or implied license or indemnity under the intellectual property rights of Lenovo orthird parties. All information contained in this document was obtained in specific environments and ispresented as an illustration. The result obtained in other operating environments may vary.Lenovo may use or distribute any of the information you supply in any way it believes appropriate withoutincurring any obligation to you.Any references in this publication to non-Lenovo Web sites are provided for convenience only and do not inany manner serve as an endorsement of those Web sites. The materials at those Web sites are not part of thematerials for this Lenovo product, and use of those Web sites is at your own risk.Any performance data contained herein was determined in a controlled environment. Therefore, the resultobtained in other operating environments may vary significantly. Some measurements may have been madeon development-level systems and there is no guarantee that these measurements will be the same ongenerally available systems. Furthermore, some measurements may have been estimated throughextrapolation. Actual results may vary. Users of this document should verify the applicable data for theirspecific environment. Copyright Lenovo 2015. All rights reserved.Note to U.S. Government Users Restricted Rights -- Use, duplication or disclosure restricted by Global Services12Administration (GSA) ADP Schedule Contract

This document REDP-5257-00 was created or updated on March 1, 2016.Send us your comments in one of the following ways: Use the online Contact us review Redbooks form found at:ibm.com/redbooks Send your comments in an email to:redbooks@us.ibm.comTrademarksLenovo, the Lenovo logo, and For Those Who Do are trademarks or registered trademarks of Lenovo in theUnited States, other countries, or both. These and other Lenovo trademarked terms are marked on their firstoccurrence in this information with the appropriate symbol ( or ), indicating US registered or common lawtrademarks owned by Lenovo at the time this information was published. Such trademarks may also beregistered or common law trademarks in other countries. A current list of Lenovo trademarks is available onthe Web at http://www.lenovo.com/legal/copytrade.html.The following terms are trademarks of Lenovo in the United States, other countries, or both:BladeCenter Flex System Lenovo Lenovo(logo) System x The following terms are trademarks of other companies:Other company, product, or service names may be trademarks or service marks of others.13

4 Lenovo UPS Quick Reference Guide RT3kVA 2U Rack or Tower UPS (100 - 125 VAC) 55943AX 2U 100 - 125 VAC 1 phase 24 A 50/60 Hz 100 VAC / 2400 VA / 2160 W / 24.0 A 120 VAC / 3000 VA / 2700 W / 25.0 A 125 VAC / 3000 VA / 2700 W / 24.0 A 6x 5-20R Fixed 2.5 m (8 ft) NEMA L5-30P RT3kVA 2U Rack or Tower UPS (200 - 240 VAC) 55943KX 2U 200 - 240 VAC 1 .