2018 INTERNATIONAL BUILDING CODE SCHEDULE OF

Transcription

2018 INTERNATIONAL BUILDING CODESCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYSERVICEY/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETED1705.1.1 Special Cases (workunusual in nature, including but notlimited to alternative materials andsystems, unusual design applications,materials and systems with specialmanufacturer's requirements - addadditional rows as needed.)Submittal review, shop (3)and/or field inspection1. Inspection of anchors post-installedin solid grouted masonry: Per researchreports including verification of anchortype, anchor dimensions, holedimensions, hole cleaning procedures,anchor spacing, edge distances,masonry unit, grout, masonrycompressive strength, anchorembedment and tightening torqueField inspectionPeriodic or as requiredby the research reportissued by an approvedsource2. Aggregate Pier Inspection: Thespecial inspector's responsibilitiesinclude, but are not limited to, review ofthe aggregate pier designer's use ofsoil parameters as presented in theproject soils report, and duringconstruction, verification of aggregateproperties, type and number of lifts ofaggregate, hole size and depths andtop elevations of the pier elements,and applied energy. Additionally,results of qualitative tests onproduction aggregate pier elementssuch as modulus load testing, upliftpull-out testing, bottom stabilizationtests and dynamic cone penetrationtests, shall be reviewed to verifycompliance with design specifications.Field inspectionPeriodic or as requiredby the research reportissued by an approvedsource1705.2.1 Structural Steel Construction1. Fabricator and erector documents(Verify reports and certificates as listedin AISC 360, Section N 3.2 forcompliance with constructiondocuments)2. Material verification of structuralsteel3. Structural steel welding:a. Inspection tasks Prior to Welding(Observe, or perform for eachwelded joint or member, the QAtasks listed in AISC 360, Table N5.41)b. Inspection tasks During Welding(Observe, or perform for eachwelded joint or member, the QAtasks listed in AISC 360, Table N5.42)c. Inspection tasks After Welding(Observe, or perform for eachwelded joint or member, the QAtasks listed in AISC 360, Table N5.43)Submittal ReviewEach submittalShop (3) and field inspectionPeriodicShop (3) and field inspectionObserve or Perform asnoted (4)Shop (3) and field inspectionObserve (4)Shop (3) and field inspectionObserve or Perform asnoted (4)d. Nondestructive testing (NDT) ofwelded joints: see Commentary2018 INTERNATIONAL BUILDING CODEB1 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYSERVICE1) Complete penetration grooveShop (3) or field ultrasonicwelds 5/16" or greater in risktesting - 100%category III or IV2) Complete penetration grooveShop (3) or field ultrasonicwelds 5/16" or greater in risktesting - 10% of welds minimumcategory II3) Welded joints subject to fatigueShop (3) or field radiographic orwhen required by AISC 360,Ultrasonic testingAppendix 3, Table A-3.14) Fabricator's NDT reports whenVerify reportsfabricator performs NDT4. Structural steel bolting:Shop (3) and field inspectiona. Inspection tasks Prior to Bolting(Observe, or perform tasks for eachbolted connection, in accordancewith QA tasks listed in AISC 360,Table N5.6-1)b. Inspection tasks During Bolting(Observe the QA tasks listed inAISC 360, Table N5.6-2)1) Pre-tensioned and slip-criticaljointsa) Turn-of-nut with matchingmarkingsb) Direct tension indicatorc) Twist-off type tension controlboltd) Turn-of-nut without matchingmarkingse) Calibrated wrench2) Snug-tight jointsc. Inspection tasks After Bolting(Perform tasks for each boltedconnection in accordance with QAtasks listed in AISC 360, Table N5.63)5. Visual inspection of exposed cutsurfaces of galvanized structural steelmain members and exposed cornersShop (3) or field inspectionof the rectangular HSS for crackssubsequent to galvanizing6. Embedments (Verify diameter,grade, type, length, embedment. SeeField inspection1705.3 for anchors)7. Verify member locations, braces,stiffeners, and application of jointField inspectiondetails at each connection comply withconstruction documentsY/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDPeriodicPeriodicPeriodicEach submittal (5)Observe or Perform asnoted (4)Observe iodicPerform (4)PeriodicPeriodicPeriodic1705.2.2 Cold-Formed Steel Deck1. Manufacturer documents (Verifyreports and certificates as listed in SDIQA/QC, Section 2, Paragraphs 2.1 and2.2 for compliance with constructiondocuments)2. Material verification of steel deck,mechanical fasteners and weldingmaterials3. Cold-formed steel deck placement:a. Inspection tasks Prior to DeckPlacement (Perform the QA taskslisted in SDI QA/QC, Appendix 1Table 1.1)b. Inspection tasks After DeckPlacement (Perform the QA taskslisted in SDI QA/QC, Appendix 1Table 1.2)4. Cold-formed steel deck welding:2018 INTERNATIONAL BUILDING CODESubmittal ReviewEach submittalShop (3) and field inspectionPeriodicShop (3) and field inspectionPerform (4)Perform (4)Shop (3) and field inspectionB2 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYa. Inspection tasks Prior to Welding(Observe the QA tasks listed in SDIQA/QC, Appendix 1 Table 1.3)b. Inspection tasks During Welding(Observe the QA tasks listed in SDIQA/QC, Appendix 1 Table 1.4)c. Inspection tasks After Welding(Perform the QA tasks listed in SDIQA/QC, Appendix 1 Table 1.5)5. Cold-formed steel deck mechanicalfastening:a. Inspection tasks Prior toMechanical Fastening (Observe theQA tasks listed in SDI QA/QC,Appendix 1 Table 1.6)b. Inspection tasks DuringMechanical Fastening (Observe theQA tasks listed in SDI QA/QC,Appendix 1 Table 1.7)c. Inspection tasks After MechanicalFastening (Perform the QA taskslisted in SDI QA/QC, Appendix 1Table 1.8)SERVICEAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDY/NObserve (4)Observe (4)Perform (4)Shop (3) and field inspectionObserve (4)Observe (4)Perform (4)1705.2.3. Open-Web Steel Joists and Joist Girders1. Installation of open-web steel joistsand joist girders.a. End connections - welding orbolted.b. Bridging - horizontal or diagonal.1) Standard bridging.2) Bridging that differs from thespecifications listed in SJI CJ orSJI 100.per SJI CJ or SJI 100Periodicper SJI CJ or SJI 100PeriodicPeriodic1705.2.4. Cold-Formed Steel Trusses Spanning 60 feet or GreaterVerify temporary and permanentrestraint/bracing are installed inaccordance with the approved trusssubmittal packageField inspectionPeriodicShop (3) and field inspectionPeriodic1705.3 Concrete Construction1. Inspection and placementverification of reinforcing steel andprestressing tendons.2. Reinforcing bar welding:a. Verification of weldability of barsother than ASTM A706.b. Inspection of single-pass fillet welds5/16 or less in size.c. Inspection of all other welds.3. Inspection of anchors cast inconcrete.4. Inspection of anchors post-installedin hardened concrete members perresearch reports, or, if no specificrequirements are provided,requirements shall be provided by theregistered design professional andapproved by the building official,including verification of anchor type,anchor dimensions, hole dimensions,hole cleaning procedures, anchorspacing, edge distances, concreteminimum thickness, anchorembedment and tightening torquea. Adhesive anchors installed inhorizontal or upward-inclinedorientation that resist sustained tensionloads.2018 INTERNATIONAL BUILDING CODEPeriodicPeriodicContinuousShop (3) and field inspectionPeriodicField inspectionPeriodic or as requiredby the research reportissued by an approvedsourceContinuousB3 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYSERVICEb. Mechanical and adhesive anchorsnote defined in 4a.5. Verify use of approved design mix6. Prior to placement, fresh concretesampling, perform slump and aircontent tests and determinetemperature of concrete and performany other tests as specified inconstruction documents.7. Inspection of concrete and shotcreteplacement for proper applicationtechniques8. Verify maintenance of specifiedcuring temperature and techniques9. Inspection of prestressed concrete:12. Inspection of formwork for shape,lines, location and dimensions13. Concrete strength testing andverification of compliance withconstruction documentsAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDPeriodicShop (3) and field inspectionPeriodicShop (3) and field inspectionContinuousShop (3) and field inspectionContinuousShop (3) and field inspectionPeriodicShop (3) and field inspectiona. Application of prestressing forceb. Grouting of bonded prestressingtendons10. Inspect erection of precastconcrete members11. Verification of in-situ concretestrength, prior to stressing of tendonsin post tensioned concrete and prior toremoval of shores and forms frombeams and structural slabsY/NContinuousContinuousPeriodicReview field testing andlaboratory reportsPeriodicField inspectionPeriodicField testing and review oflaboratory reportsPeriodic1705.4 Masonry ConstructionMINIMUM VERIFICATION REQUIREMENTS(A) Level 1, 2 and 3 Quality Assurance:1. Prior to construction,verification of compliance ofSubmittal Reviewsubmittals(B) Level 2 & 3 Quality Assurance:1. Prior to construction verificationTesting by unit strength methodof f'm and f'AAC except whereor prism test methodspecifically required by the code2. During construction, verificationof Slump Flow and Visual StabilityTesting by unit strength methodIndex (VSI) when selfor prism test methodconsolidating grout is delivered toproject site.(C) Level 3 Quality Assurance:1. During construction, verification Testing by unit strength methodof f'm and f'AAC for every 5,000 SFor prism test method2. During construction, verificationof proportions of materials asdelivered to the project site forpremixed or preblended mortar,Field inspectionprestressing grout, and groutother than self-consolidatinggrout.MINIMUM SPECIAL INSPECTION REQUIREMENTS(D) Levels 2 and 3 Quality Assurance:1. As masonry construction begins, verify that the following are ina. Proportions of the site-preparedField inspectionmortarb. Grade and size of prestressingField Inspectiontendons and anchorages2018 INTERNATIONAL BUILDING CODEPrior to ConstructionPrior to icB4 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYc. Grade, type, and size ofreinforcement, anchor bolts, andprestressing tendons andanchoragesd. Prestressing techniquee. Properties of thin-bed mortarfor AAC masonrySERVICEField InspectionField InspectionAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDPeriodicPeriodic(b)Field Inspection(b) Required for the first 5,000 square feet(c) Required after the first 5,000 square feetf. Sample panel constructionY/NLevel 2 - Continuous(c)Level 2 - PeriodicLevel 3 - ContinuousField InspectionLevel 2 - PeriodicLevel 3 - Continuous2. Prior to grouting, verify that the following are in compliance:a. Grout spaceField Inspectionb. Placement of prestressingField Inspectiontendons and anchoragesc. Placement of reinforcement,Field inspectionconnectors, and anchor boltsd. Proportions of site-preparedgrout and prestresssing grout forField Inspectionbonded tendons3. Verify compliance of the following during construction:a. Materials and procedures withField inspectionthe approved submittalsb. Placement of masonry unitsField Inspectionand mortar joint constructionc. Size and location of structuralField inspectionmembersLevel 2 - PeriodicLevel 3 - ContinuousPeriodicLevel 2 - PeriodicLevel 3 - ContinuousPeriodicPeriodicPeriodicPeriodicLevel 2 - Periodicd. Type, size, location of anchors,including other details ofanchorage of masonry tostructural members, frames, orother constructionField inspectione. Welding of reinforcementField inspectionContinuousf. Preparation, construction, andprotection of masonry during coldweather (temperature below 40oF)or hot weather (temperatureabove 90oF)Field inspectionPeriodicField testingContinuousField inspectionContinuousg. Application and measurementof prestressing forceh. Placement of grout andprestressing grout for bondedtendons is in compliancei. Placement of AAC masonryunits and construction of thin-bedmortar jointsField inspection(b) Required for the first 5,000 square feet(c) Required after the first 5,000 square feet4. Observe preparation of groutspecimens, mortar specimens, and/orprismsLevel 3 - ContinuousLevel 2 - Continuous(b)Level 2 - Periodic(c)Level 3 - ContinuousLevel 2 - PeriodicField inspectionLevel 3 - Continuous1705.5 Wood Construction1. For prefabricated wood structuralelements, inspection of the fabricationprocess and assemblies in accordancewith Section 1704.2.5.2. For high-load diaphragms, verifygrade and thickness of structural panelsheathing agree with approvedbuilding plans.2018 INTERNATIONAL BUILDING CODEIn-plant review (3)PeriodicField inspectionPeriodicB5 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITY3. For high-load diaphragms, verifynominal size of framing members atadjoining panel edges, nail or staplediameter and length, number offastener lines, and that spacingbetween fasteners in each line and atedge margins agree with approvedbuilding plans4. Metal-plate-connected woodtrusses:a. Verification that permanentindividual truss memberrestraint/bracing has been installed inaccordance with the approved trusssubmittal package when the trussheight is greater than or equal to 60".b. For trusses spanning 60 feet orgreater: verify temporary andpermanent restraint/bracing areinstalled in accordance with theapproved truss submittal packageSERVICEY/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDField inspectionPeriodicField inspectionPeriodicField inspectionPeriodic1. Verify materials below shallowfoundations are adequate to achievethe design bearing capacity.Field inspectionPeriodic2. Verify excavations are extended toproper depth and have reached propermaterial.Field inspectionPeriodicField inspectionPeriodicField inspectionContinuousField inspectionPeriodicField inspectionContinuousField inspectionContinuousField inspectionContinuousField inspectionContinuousSee Section 1705.2See Section 1705.2See Section 1705.3See Section 1705.3Field inspectionIn accordance withconstructiondocuments1705.6 Soils3. Perform classification and testing ofcompacted fill materials.4. Verify use of proper materials,densities, and lift thicknesses duringplacement and compaction ofcontrolled fill5. Prior to placement of controlled fill,inspect subgrade and verify that sitehas been prepared properly1705.7 Driven Deep Foundations1. Verify element materials, sizes andlengths comply with requirements2. Determine capacities of testelements and conduct additional loadtests, as required3. Inspect driving operations andmaintain complete and accuraterecords for each element4. Verify placement locations andplumbness, confirm type and size ofhammer, record number of blows perfoot of penetration, determine requiredpenetrations to achieve designcapacity, record tip and butt elevationsand document any damage tofoundation element5. For steel elements, performadditional inspections per Section1705.26. For concrete elements and concretefilled elements, perform tests andadditional inspections per Section1705.37. For specialty elements, performadditional inspections as determinedby the registered design professionalin responsible charge1705.8 Cast-in-Place Deep Foundations2018 INTERNATIONAL BUILDING CODEB6 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITY1.Inspect drilling operations andmaintain complete and accuraterecords for each element2. Verify placement locations andplumbness, confirm elementdiameters, bell diameters (ifapplicable), lengths, embedment intobedrock (if applicable) and adequateend-bearing strata capacity. Recordconcrete or grout volumes3. For concrete elements, performtests and additional inspections inaccordance with Section 1705.3SERVICEY/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDField inspectionContinuousField inspectionContinuousSee Section 1705.3See Section 1705.3Field inspectionContinuousShop inspectionAs noted in eachapplicable shop activity1705.9 Helical Pile FoundationsVerify installation equipment, piledimensions, tip elevations, final depth,final installation torque and otherinstallation data as required byconstruction documents.1705.10 Fabricated items1. List of fabricated items requiringspecial inspection during fabrication:2. List of fabricated items to befabricated on the premises of afabricator approved to perform suchwork without special inspection(including name of approved agencyproviding periodic auditing):1705.11.1 Structural Wood Special Inspections For Wind Resistance1. Inspection of field gluing operationsof elements of the main windforceresisting system2. Inspection of nailing, bolting,anchoring and other fastening ofcomponents within the main windforceresisting system, including wood shearwalls, wood diaphragms, drag struts,braces and hold-downs.Field inspectionContinuousShop (3) and field inspectionPeriodic1705.11.2 Cold-formed Steel Special Inspections For Wind Resistance1.Inspection during welding operationsof elements of the main windforceresisting system2. Inspection of screw attachment,bolting, anchoring and other fasteningof components within the mainwindforce-resisting system, includingshear walls, braces, diaphragms,collectors (drag struts) and holddowns.Shop (3) and field inspectionPeriodicShop (3) and field inspectionPeriodic1705.11.3 Wind-resisting Components1. Roof covering, roof deck and roofframing connections.2. Exterior wall covering and wallconnections to roof and floordiaphragms.Shop (3) and field inspectionPeriodicShop (3) and field inspectionPeriodic1705.12.1 Structural Steel Special Inspections for Seismic Resistance1. Seismic force-resisting systems inSDC B, C, D, E, or F.2. Structural steel elements in SDC B,C, D, E, or F other than those in Item1. including struts, collectors, chordsand foundation elements.Shop (3) and field inspectionIn accordance withAISC 341Shop (3) and field inspectionIn accordance withAISC 3411705.12.2 Structural Wood Special Inspections for Seismic Resistance2018 INTERNATIONAL BUILDING CODEB7 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYSERVICEY/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETED1. Field gluing operations of elementsof the seismic-force resisting systemfor SDC C, D, E or F.Field inspectionContinuous2. Nailing, bolting, anchoring and otherfastening of components within theseismic-force-resisting systemincluding wood shear walls, wooddiaphragms, drag struts, shear panelsand hold-downs for SDC C, D, E or F.Shop (3) and field inspectionPeriodic1705.12.3 Cold-formed Steel Light-Frame Construction Special Inspections for Seismic Resistance1. During welding operations ofelements of the seismic-force-resistingsystem for SDC C, D, E or F.Shop (3) and field inspectionPeriodic2. Screw attachment, bolting,anchoring and other fastening ofcomponents within the seismic-forceresisting system including shear walls,braces, diaphragms, collectors (dragstruts) and hold-downs for SDC C, D,E or F.Shop (3) and field inspectionPeriodic1705.12.4 Designated Seismic Systems Verification Special Inspections for Seismic ResistanceFor SDC C, D, E or F, inspect andverify that that the component label,anchorage or mounting conforms tothe certificate of compliance inaccordance with ASCE 7 Section13.2.2.Field inspectionPeriodic1705.12.5 Architectural Components Special Inspections for Seismic Resistance1. For SDC D, E or F, inspectionduring the erection and fastening ofexterior cladding and interior or exteriorveneer more than 30 feet above gradeor walking surface and weighing morethan 5 psf.Field inspectionPeriodic2. For SDC D, E or F, inspectionduring the erection and fastening ofinterior nonbearing walls more than 30feet above grade or walking surfaceand weighing more than 15 psf.Field inspectionPeriodicField inspectionPeriodic3. For SDC D, E or F, inspectionduring the erection and fastening ofexterior nonbearing walls more than 30feet above grade or walking surface.4. For SDC D, E or F, inspectionduring anchorage of access floors1705.12.6 Plumbing, Mechanical and Electrical Components Special Inspections for Seismic Resistance1. Inspection during the anchorage ofelectrical equipment for emergency orstandby power systems in SDC C, D,E or FField inspectionPeriodic2. Inspection during the anchorage ofother electrical equipment in SDC E orFField inspectionPeriodicField inspectionPeriodicField inspectionPeriodic3. Inspection during installation andanchorage of piping systems designedto carry hazardous materials, and theirassociated mechanical units in SDC C,D, E or F4. Inspection during the installation andanchorage of HVAC ductworkdesigned to contain hazardousmaterials in SDC C, D, E or F2018 INTERNATIONAL BUILDING CODEB8 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITYSERVICE5. Inspection during the installation andanchorage of vibration isolationsystems in SDC C, D, E or F wherenominal clearance of 1/4 inch or lessis required by the approvedconstruction documents6. Inspection during installation ofmechanical and electrical equipment,including duct work, piping systemsand their structural supports, whereautomatic fire sprinkler systems areinstalled in structures assigned to SDCC, D, E, or F to verify one of thefollowing unless flexible sprinkler hosefittings are used:a. ASCE/SEI 7, Section 13.2.3minimum required clearances havebeen provided.b. A three inch or greater nominalclearance has been provided betweenfire protection sprinkler system dropsand sprigs and: structural membersnot used collectively or independentlyto support the sprinklers; equipmentattached to the building structure; andother systems' piping.Y/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDField inspectionPeriodicField inspectionPeriodicField inspectionPeriodic1705.12.7 Storage Racks Special Inspections for Seismic ResistanceInspection during the anchorage ofstorage racks 8 feet or greater inheight in structures assigned to SDCD, E or F.Field inspectionPeriodicShop and field inspectionPeriodic1705.12.8 Seismic Isolation SystemsInspection during the fabrication andinstallation of isolator units and energydissipation devices used as part of theseismic isolation system in structuresassigned to SDC B, C, D, E or F.1705.12.9 Cold-formed Steel Special Bolted Moment FramesInspection of installation of cold-formedsteel special bolted moment frames inthe seismic force-resisting systems instructures assigned to SDC D, E or F.Field inspectionPeriodic1705.13.1 Structural Steel Testing for Seismic Resistance1. Nondestructive testing of structuralsteel in the seismic force-resistingsystems in accordance with AISC 341in structures assigned to SDC B, C, D,E or F.2. Nondestructive testing of structuralsteel elements in the seismic forceresisting systems not covered in 1above including struts, collectors,chords and foundation elements inaccordance with AISC 341 instructures assigned to SDC B, C, D, Eor F.Field testPeriodicField testPeriodic1705.13.2 Seismic Certification of Nonstructural ComponentsReview certificate of compliance fordesignated seismic systemcomponents in structures assigned toSDC B, C, D, E or F.Certificate of compliance reviewEach submittal1705.13.3 Seismic Certification of Designated Seismic SystemsReview certificate of compliance fordesignated seismic systemcomponents in structures assigned toSDC C, D, E or F2018 INTERNATIONAL BUILDING CODECertificate of compliance reviewEach submittalB9 of B10

SCHEDULE OF SPECIAL INSPECTIONS SERVICESPROJECTMATERIAL / ACTIVITY1705.13.4 Seismic Isolation SystemsTest seismic isolation system inaccordance with ASCE 7 Section 17.8in structures assigned to SDC B, C, D,E or F.SERVICEPrototype testingY/NAPPLICABLE TO THIS PROJECTEXTENTAGENT*DATE COMPLETEDPer ASCE 71705.14 Sprayed Fire-resistant Materials1. Verify surface condition preparationof structural members2. Verify minimum thickness ofsprayed fire-resistant materials appliedto structural members3. Verify density of the sprayed fireresistant material complies withapproved fire-resistant design4. Verify the cohesive/adhesive bondstrength of the cured sprayed fireresistant material5. Condition of finished applicationField inspectionPeriodicField inspectionPeriodicField inspection and testingPer IBC Section1705.14.5Field inspection and testingPer IBC Section1705.14.6Field inspectionPeriodic1705.15 Mastic and Intumescent Fire-Resistant CoatingsInspect and test mastic andintumescent fire-resistant coatingsapplied to structural elements anddecks per AWCI 12-BField inspection and testingPeriodic1705.16 Exterior Insulation and Finish Systems (EIFS)Inspection of water-resistive barrierover sheathing substrateField inspectionPeriodic1705.17 Fire-Resistant Penetrations and Joints1. Inspect penetration firestop systems2. Inspect fire-resistant joint systemsField testingField testingPer ASTM E2174Per ASTM E23931. Leakage testing and recording ofdevice locations prior to concealmentField testingPeriodic2. Prior to occupancy and aftersufficient completion, pressuredifference testing, flow measurements,and detection and control verificationField testingPeriodic1705.18 Smoke Control Systems* INSPECTION AGENTSFIRM1.2.3.4.ADDRESSTELEPHONE NO.Notes: 1. The inspection and testing agent(s) shall be engaged by the Owner or the Owner's Agent, and not by the Contractor or Subcontractor whose work is to beinspected or tested. Any conflict of interest must be disclosed to the Building Official prior to commencing work. The qualifications of the Special Inspector(s)and/or testing agencies may be subject to the approval of the Building Official and/or the Design Professional.2. The list of Special Inspectors may be submitted as a separate document, if noted so above.3. Shop Inspections of fabricated items are not required where the fabricator is approved in accordance with IBC Section 1704.2.5.1and listed in activity 1709.2.4. Observe: Observe on a random basis, operations need not be delayed pending these inspections. Perform: These tasks shall be performed for each weldedjoint, bolted connection, or steel element.5. NDT of welds completed in an approved fabricator's shop may be performed by that fabricator when approved by the AHJ. Refer to AISC 360, N6.Are Special Inspections for Seismic Resistance included in the Statement of Special Inspections ?Are Special Inspections for Wind Resistance included in the Statement of Special Inspections ?YesYesNoNoDATE:2018 INTERNATIONAL BUILDING CODEB10 of B10

in AISC 360, Section N 3.2 for compliance with construction documents) Submittal Review Each submittal 2. Material verification of structural steel Shop (3) and field inspection Periodic 3. Structural steel welding: a. Inspection tasks Prior to Welding (Ob