Transcription
MID ATS Messaging Management Center(MID AMC) Project Plan1
ObjectiveTo present the progress has been done towardestablishment of the ATS Messaging Managementcenter in the ICAO MID Region (MID AMC).2
Presentation Outline BackgroundThe need for MID AMCMID AMC Project PlanConclusions3
AMHS Implementation in the MID Six (6) states have operational AMHS links. Three (3) states have signed a contract with vendorsto purchase AMHS systems. Four (4) states have AMHS system in place but not yetoperational Two states (2) have not provide any info about AMHSImplementation plan . Two AMHS networks (Triangle) in the ICAO MIDRegion:“Amman- Cairo-Jeddah”“Amman- Jeddah- Abu Dhabi)4
LIBYASudanOperational AMHSAMHS facility in placeSigned contract with a vendorNo Info5
Presentation Outline BackgroundThe need for MID AMCMID AMC Project PlanConclusions6
The need for MID AMCMID COM centers participate in EUR-AMC as external COMoperators that have access to some of the operationalfunctions, but they can't use an important function likerouting management which is currently available to EUR AMCoperators.The Aeronautical fixed telecommunication network in theMID Region has some operational issues like Asymmetricroutes which can cause message loss.The Routing function can integrates AMHS routing withAFTN/CIDIN routing, and ensure optimal consistent routes.7
Problems in operational AMHS net.1. Asymmetric routing2. Routing to other ICAO area in AMHS5/7/20118
The Good9
AreaOEOutgoing channelJordan (AFTN)UNKNOWN ADSOSDIYFYYConvert SVC ADS UNKNOWN into NDRAreaOutgoing channelDD OSDIYFYYOS5/7/2011Jordan (AMHS)10
The Ugly11
AreaOEOutgoing channelEgypt (AFTN)UNKNOWN ADSOSDIYFYYSubject messagedid not pass thisgateway, SVC ADS UNKNOWNconveyed as IPMAreaOutgoing channelDD OSDIYFYYOSJordan (AMHS)The ATSoriginatorreceives servicemsg SVC ADS UNKNOWNinstead of NDR.5/7/201112
eThe worst13
AreaOEOutgoing channelKuwait (AMHS)OSDIYAXX isunknown address,Syria sends NDRThe translation of NDRinto service msg SVCADS UNKNOWNfails as the subjectmessage did not passthis gateway.AreaOSOutgoing channelJordan (AMHS)/C XX/ADMD ICAO/PRMD OS/O AFTN/OU OSDIYAXXThe originator is notinformed aboutmessage loss.5/7/201114
Problems in operational AMHS net.1. Asymmetric routing2. Routing to other ICAO area in AMHS5/7/201115
rnativeINDONESIAchannelWBahrainJordan5/7/2011SVC ATTN SUP ON DUTYHOLD YR TFC TO W AREANO ROUTE AVAILABLEIndia16
Presentation Outline BackgroundThe need for MID AMCMID AMC Project PlanConclusions17
MID AMC Project Plan1. Project Stakeholders: Jordan Civil Aviation Regulatory Commission ( projectsponsor )MID StatesICAOEUROCONTROLMID AMC Project ManagerMID AMC Project AssistantMID AMC Support TeamMID AMC Operators18
MID AMC Project Plan2. MID AMC Project Goals-To facilitate transition from AFTN/CIDIN to AMHS.To support states with AMHS in operation or on theirway to implement.To provide Routing management function that canensure optimum consistent routes.To provide an electronic tool to keep ANP FASID dataup-to-date.19
MID AMC Project Plan3. Deliverables: Development of MID AMC projectSynchronization with European AMCTraining for MID AMC UsersDevelopment of MID AMC manualsLaunch of the MID AMC project20
4 . MID AMC Project Plan ScheduleTaskResponsibilityDelivery DateAcquiring Technical and operational ICAO MID officespecificationsofAMCfromEUROCONTROL, and sign the agreementfor Copyrights and patent usage.20/11/2011DoneDevelop technical specifications for MIDAMC ProjectMID AMC Team7/12/2011DoneTendering process (Launch a tender,Evaluation of tenders, Purchasing order)Jordan CARCMID AMC Team5/1/2012DonePhase 1 development (Including NetworkInventory function, Address Managementfunction, Miscellaneous)MID AMCSupport Team10/5/2012DoneFactory Testing Acceptance (FAT) –phase1MID AMC18/5/2012support team and DoneProject team21
MID AMC Project Plan Schedule (Cont’d)TaskResponsibilityDelivery DateRefresher External AMC user course forMID AMC operatorsMID AMCProjectManager12/4/2012DoneDevelopment a synchronization procedurewith European AMC-MID AMCTeam-ICAO MIDoffice-EurocontrolJune/2012DonePhase 2 development (RoutingManagement, Statistics)MID AMCSupport Team13/6/2012DoneFactory Testing Acceptance (FAT) – phase 2 MID AMCsupport teamand Projectteam20/6/2012Done22
MID AMC Project Plan Schedule (Cont’d)TaskResponsibilityDelivery DateMID AMC ImplementationMID AMCsupport team30/6/2012DoneTraining on MID AMC operation- MID AMCProjectmanager- MID AMCsupport team2-5/7/2012Theoreticalpart doneSite acceptance Test (SAT)- MID AMCSupport &project Team12/7/2012DoneSign MOUs with MID states-Jordan CARC-MID states-ICAO MIDofficeOngoing23
MID AMC Project Plan Schedule (Cont’d)TaskResponsibilityDelivery DateDevelop operational specification manualsfor all MID user types (MID AMC Operator,MID AMC user, Read only users, ExternalAMC User)MID AMCProject Team12/7/2012OngoingTraining for MID AMC users ( MID states)MID AMCProjectManager1//7/2012No PlanSubmit data to MID AMC- MID states- MID AMCoperator12/7/2012DoneLaunch of the MID AMC trial periodMID AMCSupport &project Team12/12/2012Done24
MID AMC Project Plan Schedule (Cont’d)TaskResponsibilityDelivery DateDevelop Computer based training packagefor MID AMC OperatorCBT Team15/5/2013OngoingTraining for MID AMC users ( MID states)CBT Team20/12/2013Provide regular feedback to ICAO office and MID statesMID AMCFinal Evaluation for MID AMC (Go-Nogo)MID AMC TeamMID StatesLaunch of the MID AMCMSG /MIDANPIRGOngoingduring the trialperiod25
MID AMC Project Plan5. Human Resources Plan:- MID AMC Project Manager:- MID AMC Project Assistant:-MID AMC operation team:-MID AMC Support team:Mona AnnaddafEid OthmanEid OthmanYaser ZayyadZakaria HussienMajdolin Al-tradMaysoon OweinehMona AnnaddafEid OthmanYaser ZayyadMID AMC Supplier26
Presentation Outline BackgroundThe need for MID AMCMID AMC Project PlanConclusions27
Conclusions The Benefits of the project justifies the efforts andexpenditure for the its implementation. The benefits are maximized if the implementation isextended to the most of the region States. The active participation of MID States by using MID-AMCin trial period and provision of regular feedback about theoperation and performance will add value to the success ofproject.28
Conclusions States signature of the Memorandum of Agreement MOAwill reflect the commitment of the region to theharmonization, integration and coordination with the otherregions and on international level.29
30
MID AMC Project Plan Schedule (Cont'd) 24 Task Responsibility Delivery Date 12/7/2012 Ongoing MID AMC Project Team Develop operational specification manuals for all MID user types (MID AMC Operator, MID AMC user, Read only users, External AMC User) 1//7/2012 No Plan MID AMC Project Manager Training for MID AMC users ( MID states) 12/7/2012 .