MasterFlow 936 AN - Master Builders Solutions

Transcription

MasterFlow 936 ANPure epoxy (3:1) resin based high performance anchoring groutDESCRIPTIONMasterFlow 936 AN is a two component (3:1)pure epoxy resin based high performanceanchoring grout for use in cracked and uncrackedconcrete under normal as well as seismicconditions (seismic category C1 and C2).Designed for post-installed rebar connectionapplications, MasterFlow 936 AN offers a veryhigh load-bearing capacity.The system can be installed in percussive anddiamond drilled dry, wet and flooded holes.TYPICAL APPLICATIONSStructural applications in cracked anduncracked concrete applications in seismiczones (C1 and C2) Post installed rebar connections Crash barriers Structural steel APPROVALS & TESTSETA according ETAG 001 Part 1 & 5Option 1 for anchoring of threaded barsinto cracked & uncracked concreteapplication in seismic zones (C1 and C2) ETA according to TR023 for post-installedrebar connections Tested according to LEED 2009 EQ c4.1,SCAQMD rule 1168 (2005) Fire resistance F240 for reinforcing bars A as per French VOC Regulation WRAS – Suitable for use with potable waterADVANTAGES Fixings close to free edges Fire tested Versatile Anchoring without expansion pressure Ultra High load capacities Available in side-by-side cartridges Component volume ratio of 3:1 Extended gel/open time Suitable for diamond-drilled holes Suitable for dry and wet holesPACKAGINGMasterFlow 936 AN is available in boxes of 12side-by-side cartridges of 585 ml.APPLICATION GUIDELINESPlease refer to the method statement or contactMaster Builders Solutions Technical Servicesdepartment. European Technical Assessment asterFlow936AN.DoPMF936ANTR023. ETAG 001-Part 1 andPart 5 used as an EAD. For fixingand/or supporting concrete structuralelements or heavy units such ascladding and suspended ceilings.European Technical Assessment ETA17/0153. BASF Construction SolutionsGmbH. 15. 1020. MasterFlow 936 AN.DoP MF936AN. ETAG 001 Part 1 andPart 5, edition 2013, used as EAD. Forfixing and/or supporting to concrete,structural elements (which contributesto the stability of the works) or heavyunits.

MasterFlow 936 ANWORKING & LOADING TIMESBase MaterialTemperature 10to 15 C25 mins 15 to 20 C18 mins 20 to 25 C12 mins 25 to 30 C8 mins 30 to 35 C6 mins 35 to 40 CEnsure cartridge is 10 CResin cartridge Temperature 10 to 15 CT Work40 mins 15 to 20 C 20 to 25 C 25 to 30 C 30 to 35 C 35 to 40 CT Load18 hrs12 hrs8 hrs6 hrs4 hrs2 hrsNote: T Work is at the highest temperature in the range. T load is at the lowest temperature in the rangePHYSICAL PROPERTIESPropertyUnitDensityg/cm³1.524 hoursN/mm²757 daysN/mm²9524 hoursN/mm²187 daysN/mm²23Compressive StrengthTensile Strength24 hoursElongation at Break7 daysTensile ModulusFlexural StrengthHDTValueASTM D 1875 @ 20 C / 72 FASTM D 695 @ 20 C / 72 FASTM D 638 @ 20 C / 72 F6.6%Test StandardASTM D 638 @ 20 C / 72 F5.924 hoursGN/m²5.77 daysGN/m²5.524 hoursN/mm²45ASTM D 790 @ 20 C / 72 F7 days C49ASTM D 648 @ 20 C / 72 Fg/L4.5ASTM D 2369VOCASTM D 638 @ 20 C / 72 FTHEORETICAL NUMBER OF FIXINGS PER CARTRIDGEApplies to installations in solid substrates onlyCartridge Volume585 mlside by sidehef8d10d12d20dØ8Drilling Ø10mmØ10Ø12Ø16Ø20Ø24Ø27Ø30Drilling Ø12mmDrilling Ø14mmDrilling Ø18mmDrilling Ø22mmDrilling Ø26mmDrilling Ø30mmDrilling 11714117118746442Note: Jobsite/contractor installations usually result in more resin being injected than the theoretical requirement resulting in lowernumber of fixings per cartridge. The reduction to the number of fixings per cartridge in practice is greater for smaller diameter holesand shallower embedment depths.

MasterFlow 936 ANMasterFlow 936 AN with REINFORCING BARS (ANCHOR THEORY)INSTALLATION PARAMETERSDiameter of rebar (mm)Drilled hole diameter (mm) 812 1014 1216 1620 2025 2532 3240 880 1090 12110 16 20170 25210 32160.85DESIGN RESISTANCERebar sizeEffective embedment depth hef[mm]125300non-cracked 90.00147.33tensioncracked 90.00147.33 880 1090 12110 16 20 25210 32non-cracked concreteC20/25NRec,p ensioncracked 4.29105.24tensionshearRECOMMENDED RESISTANCERebar sizeEffective embedment depth heftensionshear[mm]125170300Steel strength must also be considered and the lowest value controls.Partial safety factor 1.4For resistance values in higher temperatures, please contact Master Builders Solutions Technical Services.All the above resistance values are considering combined pull out and concrete cone failure in tension and steel failure in shear.The above load values are for long term temperature of -40 C to 50 C and short-term temperature of 70 C

MasterFlow 936 ANMasterFlow 936 AN with THREADED RODSINSTALLATION PARAMETERSDiameter of threaded rod (mm)Drilled hole diameter 20M24M30809011012817021027022.79DESIGN RESISTANCEThreaded Rod sizeEffective embedment depth heftensionsheartensionshear[mm]non-cracked 0112.00cracked RECOMMENDED RESISTANCEThreaded Rod sizeEffective embedment depth hef[mm]non-cracked .0022.2934.8650.2980.00cracked 22.2934.8650.2980.00Steel strength must also be considered and the lowest value controls.Partial safety factor 1.4Design resistance and recommended resistance in tension are only valid for single anchors without close edge considerations forcombined pullout and concrete cone failure and concrete cone failure. Steel failure is not considered by these calculations.Design resistance and recommended resistance in shear are only valid for single anchors for steel failure without lever arm.The above load values are for long term temperature of -40 C to 50 C and short-term temperature of 70 C

MasterFlow 936 ANSTORAGE AND SHELF LIFECartridges should be stored in their originalpackaging, the correct way up and in cool dryconditions ( 5 C to 25 C) out of direct sunlight.When stored correctly, the shelf life will be for 12months from the date of manufacture.QUALITY AND CAREAll products originating from Master BuildersSolutions Dubai, UAE facility are manufacturedunder a management system independentlycertified to conform to the requirements of thequality, environmental and occupational health &safety standards ISO 9001 and ISO 14001.* Properties listed are based on laboratory controlled tests. Registered trademark of the MBCC Group in many countries.MBS CC-UAE/Fl 936AN 10 15/v6/02 18/v7/09 18/v8/09 19/v9/02 21The technical information and application advice given in this Master Builders Solutions publication are based onSTATEMENT OF the present state of our best scientific and practical knowledge. As the information herein is of a general nature, noRESPONSIBILITY assumption can be made as to a product's suitability for a particular use or application and no warranty as to itsaccuracy, reliability or completeness either expressed or implied is given other than those required by law. The useris responsible for checking the suitability of products for their intended use.NOTEField service where provided does not constitute supervisory responsibility. Suggestions made by Master BuildersSolutions either orally or in writing may be followed, modified or rejected by the owner, engineer or contractor sincethey, and not Master Builders Solutions, are responsible for carrying out procedures appropriate to a specificapplication.Master Builders SolutionsConstruction Chemicals LLCP.O. Box 37127, Dubai, UAETel: 971 4 laimer: the TUV markrelates to certified managementsystem and not to the productmentioned on this datasheet

Pure epoxy (3:1) resin based high performance anchoring grout DESCRIPTION MasterFlow 936 AN is a two component (3:1) pure epoxy resin based high performance anchoring grout for use in cracked and uncracked concrete under normal as well as seismic conditions (seismic category C1 and C2). Designed for post-installed rebar connection