Value Focused. Results Driven. Planning Work With Maximo Scheduler

Transcription

value focused. results driven.Planning work with Maximo SchedulerFor Audio:Phone: 1-888-296-6500Code:738859#

Agenda Why Maximo Asset Management Scheduler? What is Maximo Asset Management Schedule? Work Orders Scheduler Assignment Manager PM Forecasts Demonstration Questions?

Why?What IBM heard from their Customers: Need the ability to visualize work schedules and related labor resources. Third party planning tools are too heavy for ‘everyday’ users. Primavera, MS Project and other tools require coordination to synchronize. Needed something easier to implement than the adapters.Maximo Asset Management Scheduler was delivered in August of 2009.

What is Maximo Scheduler? A Maximo application that contains a Gantt tool to schedule work orders andtasks graphically.An add on to Maximo 7.1, requiring Maximo 7.1.1.5

Maximo Applications modified for SchedulerSchedulerGantt ViewDrag and drop work order and tasksView craft requirementsManage dependenciesPerform CPM“What if” scenariosWork OrderDate constraintsTask dependencies“Schedulable” tasksAssignment ManagerMany to many assignmentsPart of Work Order applicationBulk reschedulePM ForecastsDate and meter based forecastsEdit forecast datesView forecasts in SchedulerView craft requirementsDate constraints

Traditional Maximo Project Work Order HierarchyHard to Visualize!Hard to DetermineDependencies!

The Project can be retrieved into Scheduler via aQuery

Four Main Areas for the Gantt View

First Area: Work/Task Details Work can be filtered or“rolled up”. Hover Box providesquick look at details Go To will drill back toWork Order/Task Details can be edited Columns areconfigurable.

Second Area: Gantt View Drag to change scheduleor duration Hover Box providesquick look at details Create and ManageRelationships Alter view timescale Perform CPM Scheduling

Third/Fourth Area: Resource Details and View Drag to gantt work tochange resource levels Hover Box providesquick look at details Isolate IndividualCrafts/Skills for easierviewing Go To drills to Craft –and provides indicationof Where Used

Scheduler ScreenUsers can easily editconstraint types and lagtime.

Scheduler ScreenUsers can use Critical PathMethodology to assist inscheduling – either entireschedule or selectedactivities.

Scheduler ScreenToolbar Buttons providequick save (only toScheduler – for “what if”scenarios) or Commit (savechanges back to WorkOrders). Data can also berefreshed.

Changes to Work Order TrackingWork Orders and Taskscontain additional fields tofacilitate dependency andscheduling maintenanceoutside of Scheduler.

Preventive Maintenance ForecastsMaximo will generate PMforecasts for a selection ofPMs.

Preventive Maintenance ForecastsNew Forecast Tab will showforecasted dates. Dates canbe modified here.

Preventive Maintenance ForecastsPM Query with forecast ispulled forward intoScheduler.

Preventive Maintenance ForecastsForecasts can be reviewedand modified.

New Assignments Tab in Work Order Work can be assignedand scheduled Work can be completed New Work Assignmentscan be created.

Bulk Re-scheduling can be done from the ListTab Work can be rescheduled with sameassignments Work can be unassignedby uncheckingassignments box

value focused. results driven.Demonstration

Thank You!Jason Sadovia, CMC, PMP, CSSBBSenior ConsultantOntracks ConsultingPhone: (780) 637-4130 x224Email: jsadovia@ontrackconsulting.comWebsite: www.ontrakcsconsultng.comvalue focused. results driven.

Maximo Asset Management Scheduler was delivered in August of 2009. What is Maximo Scheduler? A Maximo application that contains a Gantt tool to schedule work orders and tasks graphically. An add on to Maximo 7.1, requiring Maximo 7.1.1.5. Maximo Applications modified for Scheduler Scheduler Work Order