162970 SHEET 01 OF 09GENERAL NOTESTHESE INSTALLATION INSTRUCTIONS ARE A SUPPLEMENT TOTHE APPROVED SHOP DRAWINGS. USE IN CONJUNCTION WITHTHOSE DRAWINGS.HANDLING, STORING AND PROTECTINGALUMINUM MATERIALG)H)CHECK ALL MATERIAL ON ARRIVAL FOR QUANTITY.K)BE SURE TO HAVE ALL THE MATERIALS AND TOOLSNEEDED TO BEGIN THE INSTALLATION.1.2.3.4.APPROVED SHOP DRAWINGS.LEVEL AND PLUMB (TRANSIT).FASTENERS AND REQUIRED DRIVERS.PERIMETERS AND ACCESSORIES SUCH AS ANCHORS,FASTENERS, SLEEVES AND/OR SPLICE CAPS.5. SEALING MATERIALS.6. GLAZING MATERIALS.HANDLE CAREFULLY - DO NOT DROP FROM THE TRUCK.STACK WITH ADEQUATE SEPARATION SO MATERIAL WILLNOT RUB TOGETHER. STORE OFF THE GROUND.PROTECT AGAINST ELEMENTS AND OTHERCONSTRUCTION TRADES.L)B)KEEP MATERIAL AWAY FROM WATER, MUD AND SPRAY PREVENT CEMENT, PLASTER AND OTHER MATERIALSFROM DAMAGING THE FINISH.C)PROTECT THE MATERIALS AFTER ERECTION, BYWRAPPING WITH KRAFT PAPER - OR BY ERECTINGVISQUEEN/CANVAS SPLATTER SCREENS. CEMENT,PLASTER, TERRAZZO AND OTHER ALKALINE MATERIALSARE VERY HARMFUL TO THE FINISH AND SHOULD BEREMOVED WITH WATER AND MILD SOAP BEFORESETTING OCCURS. UNDER NO CIRCUMSTANCES ALLOWTHESE MATERIALS TO TO DRY OR PERMANENT STAININGWILL OCCUR.GENERAL RULESTHE FOLLOWING PRACTICES ARE RECOMMENDED FOR ALLWALL INSTALLATIONS.A)READ COMPLETE INSTRUCTIONS BEFORE ORDERINGGLASS OR FABRICATING MATERIAL.B)CHECK SHOP DRAWINGS TO BECOME THOROUGHLYFAMILIAR WITH THE JOB.C)ALL MATERIALS ARE TO BE INSTALLED PLUMB, LEVELAND TRUE.D)ALL WORK SHOULD START FROM ESTABLISHED BENCHMARKS AND COLUMN CENTER LINES ESTABLISHED BYTHE ARCHITECTURAL DRAWINGS AND THE GENERALCONTRACTOR.E)F)THE SEQUENCE OF ERECTION SHOULD BECOORDINATED WITH THE JOB SUPERINTENDENT SODELAYS ARE PREVENTED AND RISK OF MATERIALDAMAGE IS MINIMIZED. IF PRESETTING OF ANCHORAGEIS REQUIRED, COORDINATE WITH GENERALCONTRACTOR AND SUPERVISE LOCATION.MAKE CERTAIN CONSTRUCTION WHICH WILL RECEIVEYOUR MATERIALS IS ACCORDING TO THE CONTRACTDOCUMENTS. IF NOT, NOTIFY THE GENERALCONTRACTOR IN WRITING AND RESOLVE DIFFERENCESBEFORE PROCEEDING WITH YOUR WORK.FOLLOW KAWNEER INSTALLATION AND GLAZINGINSTRUCTIONS.J)THE FOLLOWING PRECAUTIONS ARE RECOMMENDED TOASSURE EARLY ACCEPTANCE OF YOUR PRODUCTS ANDWORKMANSHIP.A)INSULATE ALL ALUMINUM TO BE PLACED DIRECTLY INCONTACT WITH THE MASONRY OR INCOMPATIBLEMATERIALS WITH A HEAVY COAT OF ZINC CHROMATE ORBITUMINOUS PAINT.FOLLOW SEALANT MANUFACTURER'SRECOMMENDATIONS FOR PROPER SEALANT ANDAPPLICATION. ALL SEALANTS AND MASTICS MUST BECOMPATIBLE WITH ALL SURFACES INCLUDING OTHERSEALANT SURFACES. WHERE REQUIRED ALL SEALANTSMUST ADHERE TO ALL SURFACES INCLUDING OTHERSEALANT SURFACES.REFERENCEINSTRUCTIONS162983 FOREXTERIOR FRAMEPERIMETERSOPENSIDEUPCONFIDENTIAL AND PROPRIETARY INFORMATIONKAWNEER COMPANY INC.THESE DRAWINGS ARE THE SOLE AND EXCLUSIVE PROPERTY OF KAWNEER AND CONTAINSENSITIVE, PRIVILEGED OR CONFIDENTIAL INFORMATION WHICH MAY BE USED ONLY FOR ITSBENEFIT. THE DISCLOSURE OF THESE DRAWINGS TO UNAUTHORIZED PERSONS IS STRICTLYPROHIBITED. THIS DOCUMENT AND ALL COPIES MUST BE RETURNED UPON DEMAND.COPYRIGHT KAWNEER COMPANY, INC., 2013HEAD OPENSIDEDOWNSTOOLINTERMEDIATEHORIZONTALSSILL CONDITIONOPENSIDEDOWNSHEARBLOCKSECTION A-AASILL HORIZONTALSMUST BE SHIMMEDTHE OPEN SIDE OF THE OPEN BACK HORIZONTAL IS TO BEPOSITIONED AS SHOWN BELOW. THE INTERMEDIATEHORIZONTAL IS POSITIONED OPEN SIDE DOWN FOR DEAD LOADSUPPORT.WHICH ACCEPT BOTH 1" AND 1/4" INFILLS. ALSO 1/4" FRAMINGMEMBERS WHICH ACCEPT 1/4" INFILLS ONLY ARE AVAILABLE.GLASS BITE IS 1/2" AT VERTICALS AND HORIZONTALS. GLASSSIZES MUST BE CALCULATED FROM APPROVED SHOPDRAWINGS.WHEN THE OPEN SIDE OF THE OPEN BACK HORIZONTAL ISEXPOSED AND AT EYE LEVEL A SNAP-IN FILLER IS AVAILABLE.OPENSIDEUPUNLESS OTHERWISE SPECIFIED, IT IS RECOMMENDED THATSILICONE SEALANT BE USED FOR ALL INTERNAL SEALS.SEALANT MUST BE APPLIED PER THE SEALANTMANUFACTURER'S RECOMMENDATIONS AND PASS ALLADHESION AND COMPATIBILITY TESTING. AT ALL JOINT SEALS,SEALANT MUST ADHERE TO METAL, GASKETS, THERMALSEPARATOR AND JOINT PLUG MATERIALS. CLEAN ALLSURFACES PRIOR TO APPLICATION OF SEALANT AND PRIMEWHERE NECESSARY TO ACHIEVE PROPER ADHESION.SHIM ALL SILL HORIZONTALS AT SETTING BLOCK LOCATIONS.WHEN THE SNAP-IN FILLER IS NOT USED, AND DUE TOSTANDARD COMMERCIAL EXTRUDING TOLERANCES, IT MAYBE REQUIRED TO USE A 4" PIECE OF THE FILLER AT EACH ENDOF A HORIZONTAL.USE PART 162316 FOR THE 6" DEEP SYSTEMUSE PART 162317 FOR THE 7 1/2" DEEP SYSTEMHEAD CONDITIONOPENSIDEDOWNALL INTERMEDIATEHORIZONTALSOPENSIDEDOWNSILL CONDITIONOPEN BACK HORIZONTAL NOTESTHE OPEN BACK HORIZONTAL IS TO BE TYPICALLY USED FORALL HEAD/SILL AND LAST BAY INTERMEDIATE HORIZONTALS.THE OPEN BACK HORIZONTAL CAN BE USED AT OTHERCONDITIONS IF IT IS AN ADVANTAGE TO THE JOB DESIGN.THE SHEAR BLOCK AT ALL OPEN BACK INTERMEDIATEHORIZONTALS HAS THE OPTION TO BE PRE-INSTALLED INTOTHE HORIZONTAL BEFORE HORIZONTALS ARE INSTALLEDOPEN BACK HORIZONTALSWHENEVER POSSIBLE AVOID USING OPEN BACK HORIZONTALSHORIZONTAL BECOMES ABSOLUTELY NECESSARY THE SHEARBLOCK CONNECTION WILL BE AS SHOWN BELOW.ALSO REFER TO CORNER INSTRUCTIONS 162972CURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 01 OF 09

162970 SHEET 02 OF 09STEP 1 - CHECK OPENINGSSTEP 4 - FRAME ASSEMBLYSTEP 4 - FRAME ASSEMBLYELEVATIONS AND SLABS MUST BE WITHIN ADJUSTMENT OFANCHORING SYSTEM. SEE APPROVED SHOP DRAWINGS FORALLOWABLE ADJUSTMENT.ATTACH ANCHORS TO MULLIONS WHERE APPLICABLE.ATTACH SHEAR BLOCKSANCHORING SURFACES OF PERIMETER CONSTRUCTIONMUST BE LEVEL AND PLUMB WITHIN THE ADJUSTMENTLIMITS OF THE HEAD, SILL AND JAMB. SEE APPROVED SHOPDRAWINGS FOR ALLOWABLE ADJUSTMENT.STEP 2 - LAY OUT ANCHOR ANDMULLION CENTERLINESANCHOR PREP MAY BE FABRICATED IN THE FIELDOR FACTORY. CONSULT APPROVED SHOPDRAWINGS FOR CORRECT METHOD.027477SEPARATORBETWEEN ANCHORAND MULLIONHEAD/SILL SHEAR BLOCK/ANCHORWHERE APPLICABLE AND SHOWN BELOW.THERMAL BREAKTO BE SAMELENGTH ASVERTICALMULLIONS162314 (6" SYSTEM AT JAMBS)162315 (7-1/2" SYSTEM AT JAMBS)162342 (6" SYSTEM AT MULLIONS)162343 (7-1/2" SYSTEM AT MULLIONS)WELD PLATESIZE AND SPACING OFWELD PER APPROVEDSHOP DRAWINGSVARIES WITHJOB CONDITIONSOPTION TOINSTALL THERMALBREAK AFTERVERTICALS ANDHORIZONTALSARE INSTALLEDWHEN WELDING ANCHORS, PROTECT INSTALLED GLASSAND METAL FROM WELD SPLATTER.USE COLUMN CENTER LINES ESTABLISHED BY THEGENERAL CONTRACTOR. ON EACH FLOOR LAY OUT MULLIONCENTER LINES AND ANCHOR CENTER LINES.EXTERIORFACE OFBEAM ORFLOOR SLAB162310THERMAL BREAK128394 SCREWS#12 x 1-7/8"PAN HEADTYPE BSTANDARD ANCHOR PREP IS THRU-BOLTED ATINTERMEDIATE VERTICALS AND TAPPING PLATES ARE USEDAT JAMB VERTICALS. REFER TO APPROVED SHOPDRAWINGS FOR CORRECT METHOD.USE WALL LINES ESTABLISHED BY THE GENERALCONTRACTOR. ON EACH FLOOR LAY OUT A REFERENCE LINETO ESTABLISH IN AND OUT WALL LOCATIONS.C/L OF MULLIONSTEP 5 - INSTALL THERMAL BREAKSTRUCTURAL INTEGRITY OFANCHOR AND FASTENERS MUST BECHECKED BY FACTORY ENGINEERS.ANCHOR FASTENERLOCATIONS PERAPPROVED SHOPDRAWINGSDO NOT OVER TIGHTEN ANCHOR CONNECTIONS.TIGHTEN TO A "SNUG TIGHT" POSITION WITHPARTS BROUGHT INTO GOOD CONTACT. BESURE ANY SPRING TYPE LOCK WASHERS ARECOMPRESSED. THEN TIGHTEN APPROXIMATELY1/2 MORE TURN.THERMAL BREAKTO BE 1/4"SHORT AT EACHEND OFHORIZONTALS1/4"INSTALL HEAD AND SILL END CAPS162388 (1" FRAMING)162389 (1/4" FRAMING)SET IN SEALANTSHEAR BLOCK/ANCHOR128396 SCREWS#12 x 7/16"PAN HEAD TYPE BATTACH SHEAR BLOCKS.TYPICALMULLIONTYPICAL INTERMEDIATE SHEAR BLOCKS162377 (6" SYSTEM)162378 (7-1/2" SYSTEM)STEP 5 - INSTALL THERMAL BREAKSEE APPROVED SHOPDRAWINGS FORANCHOR LAYOUTSHEAD AND SILL SHEAR BLOCKS162331 (6" SYSTEM)162332 (7-1/2" SYSTEM)STEP 3 - INSTALL PRESET ANCHORS IFAPPLICABLEUSING LOCATION LINES PREVIOUSLY ESTABLISHED INSTALLPRESET ANCHORS IN PLACE PER APPROVED SHOPDRAWINGS.REFERENCE INSTRUCTIONS 162983FOR EXTERIOR FRAME PERIMETERSHEAD AND SILL SHEAR BLOCKS162384 (6" SYSTEM)162385 (7-1/2" SYSTEM)162310NOT REQUIRED AT EXTERIORFRAME PERIMETERS SHOWN ININSTRUCTIONS 162983 AND ATOPTIONAL PERIMETER FILLERS 162022AND 162023DO NOT STRETCHWHEN REMOVINGFROM COIL ANDCARTONDO NOTSTRETCHDURINGINSTALLATIONCURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS162310THERMAL BREAK95449-11504/21/17162970 SHEET 02 OF 09

162970 SHEET 03 OF 09STEP 6 - PERIMETERS WHEREAPPLICABLESTEP 7 - INSTALL VERTICAL MULLIONS"F" OR "T" ANCHORSWHERE APPLICABLEINSTALL PERIMETER MEMBERS PER APPROVEDSHOP DRAWINGS. PERIMETER MEMBERS CANOCCUR AT HEAD, SILL OR JAMB CONDITIONS.BENCHMARK TO FACE OFPERIMETER MEMBERPER APPROVED SHOPDRAWINGS"F" AND "T"ANCHOR FASTENERLOCATIONS PERAPPROVED SHOPDRAWINGSSTEP 7 - INSTALL VERTICAL MULLIONSHEAD/SILL SHEAR BLOCK/ANCHORWHERE APPLICABLE.VERTICAL SPLICEJOINTS WHEREAPPLICABLE.CAN NOT BE USED WITH EXTERIOR FRAMEPERIMETERS SHOWN ON INSTRUCTIONS 162983162314 (6" SYSTEM AT JAMBS)162315 (7-1/2" SYSTEM AT JAMBS)162342 (6" SYSTEM AT MULLIONS)162343 (7-1/2" SYSTEM AT MULLIONS)REFERENCEINSTRUCTIONS162983 FOREXTERIOR FRAMEPERIMETERSCONTINUOUS "F" PERIMETER162017 (1" GLASS)162176 (1/4" GLASS)STEP 7 - INSTALL VERTICAL MULLIONSSLEEVE IS FACTORYTAPED INTO THEBOTTOM OF THETOP VERTICAL128284 SCREWS#12 x 1-1/2FLAT HEADTYPE ABTHESE SHEARBLOCKS MAY NEEDTO BE REMOVED TOINSTALL A ANCHORFASTENER THATMIGHT BE LOCATEDCLOSE TO THEMULLIONREMOVE THE TAPEAND LET THE SLEEVESLIDE DOWN TO THEFACTORY APPLIEDSTOP SCREW128284 SCREWS#12 x 1-1/2FLAT HEADTYPE ABFOR HORIZONTALATTACHMENTFIELD APPLIEDFIXING SCREW128348#10 x 1-1/4"FLAT HEADSELF DRILLINGTHE ABOVE SCREWS ARE ONLY USED AT THEOPTIONAL SHEAR BLOCK/ANCHORS.STRUCTURAL SHIMMING IS REQUIRED ATSILL TO ACCOMPLISH DESIGNEDPERIMETER SEAL WIDTHUSE GLAZING 162350 TEMPORARIESWITH 128406 SCREWSANCHOR FASTENERLOCATIONS PERAPPROVED SHOPDRAWINGSMAXIMUM TEMPORARY SPACING IS 30".IF MORE THAN A 50 MPH WIND ISEXPECTED INSTALL PRESSURE PLATES.STEP 7 - INSTALL VERTICAL MULLIONSDIMENSION BUILD-UP CHECK CHECKOVERALL FRAME DIMENSIONS ABOUT EVERYFIVE MULLIONS ON LONG RUNS. THIS IS TOAVOID DIMENSION BUILD-UP10 UNITS CHECK DIMENSIONSHOP APPLIEDSTOP SCREW128267#12 x 1" PAN HEADTYPE ABUSE TEMPORARYSPACERS FORJOINT DIMENSION"F" AND "T" ANCHORFASTENER LOCATIONSPER APPROVEDSHOP DRAWINGSAT MULLION JAMBSIDE, APPLY (2) 128396SCREWS AS SHOWNTO CENTER F-CLIPS ASREQUIRED.SPLICE JOINTWHEN IT OCCURSAT A HORIZONTAL1 1/4"1/8"5 UNITS CHECK DIM.SILL SHOWNHEAD SIMILARANCHOR FASTENERLOCATIONS PERAPPROVED SHOPDRAWINGSCURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 03 OF 09

162970 SHEET 04 OF 09STEP 8 - INSTALL HEAD/SILL ANDINTERMEDIATE HORIZONTALSTUBULAR HORIZONTALS128405 SCREWS#12 X 7/8"FLAT HEADTYPE ABSTEP 8 - INSTALL HEAD/SILL AND INTERMEDIATE HORIZONTALSREFERENCE INSTRUCTIONS 162983 FOREXTERIOR FRAME PERIMETERSINSTALLING CEILING INTERMEDIATEOPEN BACK HORIZONTALAAOPEN BACK HORIZONTALS AND LAST BAY HORIZONTALS.FILLER AVAILABLE WHEN OPEN BACK IS EXPOSED AND ATEYE LEVEL.128405 SCREWS#12 X 7/8"FLAT HEAD TYPE ABINSTALLING STOOL INTERMEDIATEOPEN BACK HORIZONTALHEADJOINT PLUG162321 (1" FRAMING)162322 (1/4" FRAME MEMBERS)STEP 9 - INSTALL JOINT PLUGSCEILINGALL SURFACES AND GROOVES MUST BECLEANED PER THE SEALANT MANUFACTURER'SRECOMMENDATIONS.JUST BEFORE INSTALLING JOINT PLUGSAPPLY SEALANT AS SHOWN FILLINGGASKET POCKET AND ADAPTER GROOVE.SECTION A-ASTOOLTHERMAL BREAKTO BE 1/4"SHORT AT EACHEND OF1/4HORIZONTALS"APPLY SEALANT TO THISFACE OF JOINT PLUGFILLGASKETPOCKETFILLADAPTERGROOVESEAL AROUND JOINT PLUGEDGES AND COMPLETELYOVER JOINT PLUG WITHSEALANT AND TOOLAS SHOWNSEAL AROUND JOINT PLUGEDGES AND COMPLETELYOVER JOINT PLUG WITHSEALANT AND TOOLAS SHOWNSILLREFERENCE INSTRUCTIONS 162983 FOREXTERIOR FRAME PERIMETERSFACE VIEWCURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 04 OF 09

STEP 10 - INSTALL PERIMETERFILLERS AND SPANDRELADAPTERS WHEREAPPLICABLEJUST BEFOREINSTALLING FILLERSAND SPANDRELADAPTERS, FACE SEALJOINTS AT ALL 4CORNERS. ALSO SEALSCREW HEAD AT TOPHALF OF HORIZONTALSTEP 11 - SEAL INTERIOR OFVERTICAL SPLICE JOINTS162970 SHEET 05 OF 09STEP 11 - SEAL INTERIOR OFVERTICAL SPLICE JOINTSALL SURFACES AND GROOVES MUST BECLEANED PER THE SEALANT MANUFACTURER'SRECOMMENDATIONS.ALL SURFACES AND GROOVESMUST BE CLEANED PER THESEALANT MANUFACTURER'SRECOMMENDATIONS.EXPANSION JOINTLOCATED AT AHORIZONTALSEALSEALAPPLY BONDBREAKER TAPETO FACE OF SLEEVEAPPLY BONDBREAKER TAPETO FACE OF SLEEVESPANDRELADAPTEREXPANSION JOINTLOCATED AT AHORIZONTALPERIMETER FILLERSEALSEALSPANDRELADAPTERSGROOVE FORINSTALLATIONTOOLUSE PUTTY KNIFE,SMALL PRY BAR ORSCREW DRIVERAPPLY BONDBREAKER TAPETO FACE OF SLEEVESPANDRELADAPTERSAPPLY BONDBREAKER TAPETO FACE OF SLEEVECURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 05 OF 09

162970 SHEET 06 OF 09STEP 12 - INSTALL INTERIORGLAZING GASKETSSTEP 12 - INSTALL INTERIORGLAZING GASKETSGASKETS SHOULD BE INSTALLED JUST PRIORTO GLASS TO AVOID CONTAMINATION BY JOBSITE DEBRIS. GASKET GROOVES AND POCKETSSHOULD BE CLEAN.STEP 13 - INSTALL SETTING BLOCKSSTEP 14 - INSTALL EXTERIOR GASKETSINTO PRESSURE PLATESREFERENCE GASKET NOTES IN STEP 12SAME NOTES APPLY.VISIONGASKETARRANGEMENTS SHOULD BE MADE TO WARMGASKETS BEFORE INSTALLATION. THIS WILLPREVENT EXCESSIVE GLAZING PRESSURE ONTHE GLASS DUE TO COLD, STIFF RUBBERGASKETS.REFERENCE INSTRUCTIONS 162983 FOREXTERIOR FRAME PERIMETERSSEAL ALL (4)GASKET CORNERSVISIONGASKETGASKETS CAN BECOME DEFORMED DURINGSTORAGE IN CARTONS. THEY SHOULD BEREMOVED FROM CARTONS SEVERAL HOURSPRIOR TO GLAZING AND LAID FLAT OR HUNG TOALLOW RECOVERY OF CORRECT SHAPE.ALLOW THIS.GASKET INSTALLED LENGTH TO BE DAYLITEOPENING. GASKETS TO BE CUT LONG FORSOME "CROWD-IN". GASKETS SHOULD NEVERBE " STRETCHED TO FIT".GASKET027850SEALALL (4)GASKETCORNERSSPANDREL GASKETSEAL THE JAMBADAPTERS 6" UPFROM THE BOTTOM"CROWD-IN" TO BE 1/8" PER FOOT UP TO 5"-0",3/16" PER FOOT UP TO 8'-O", 1/4" PER FOOTOVER 8'-0".JUST BEFOREINSTALLING VERTICALAND HORIZONTALGASKETS FACE SEALJOINTS AT ALL (4)CORNERS. ALSO SEALSCREW HEAD AT TOPHALF OF HORIZONTALSEAL ALL (4)SPANDRELADAPTERCORNERSSEAL T027857LOCATE SETTING BLOCKS PERAPPROVED SHOP DRAWINGS ORDEADLOAD CHARTSVERTICAL GASKETS ARETO RUN CONTINUOUSEXCEPT AT HEAD ANDSILL CONDITIONS THEGASKET IS TO BECUT 1" SHORT THIS ISFOR THE SEAL ATSECTION D-DSTEP 17 - SHEET # 8PERIMETER PRESSUREPLATE1"SEALALL (4)GASKETCORNERSVISIONGASKETPERIMETER WHEREAPPLICABLE1" SETTINGBLOCK 0278531"HORIZONTAL GASKET TO BESAME LENGTH AS PRESSUREPLATESPANDRELGASKETSET GASKETS INFRESH SEALANTAT EXPANSIONJOINTS. TRIMGASKET DARTOR CURED JOINTSEALANT TOCREATE A AIRTIGHT SEAL.PERIMETERWHERE APPLICABLEGASKET 027857 ATONE SIDE. DO NOTCUT 1" SHORT.1/4" SETTINGBLOCK 027854CURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 06 OF 09

STEP 15 - INSTALL GLASSSTEP 16 - INSTALL GLASS SIDE BLOCKS162970 SHEET 07 OF 09STEP 17 - INSTALL EXTERIORPRESSURE PLATESUSE 162350 GLAZING TEMPORARIESAS REQUIRED. USE 128406 SCREWSGLASS EDGEGLASS EDGERECOMMEND USING TORQUE LIMITTOOL 162399 SEE NOTE.AHOW TO SET TORQUE LIMITAVISIONGLASSABAB1) ATTACH ANY CALIBRATED TORQUE INDICATOR TOOUTPUT STUB (1) AND DETERMINE PRESENT TORQUESETTING WHILE HOLDING THE BODY (5), OR VICE-VERSA.2) REMOVE SNAP RING (2) AND LOCKING PLATE (3).CENTEROF GLASSHEIGHT3) ADJUST NUT (4) WITH OPEN-END WRENCH : CLOCKWISETO INCREASE TORQUE, COUNTER- CLOCKWISE TODECREASE TORQUE.4) OBTAIN NEW TORQUE READING WITH THE CALIBRATEDTORQUE INDICATOR. REPEAT PRECEDING STEP IF MOREADJUSTMENT IS NECESSARY TO REACH DESIRED LIMIT.MAXIMUM TEMPORARY SPACING IS 30".IF WINDS GREATER THAN 50 MPH (80KPH) ARE EXPECTED,ADDITIONAL TEMPORARIES MAY BE REQUIRED. CONSULTYOUR SEALANT AND/OR INFILL SUPPLIER FOR SPACINGRECOMMENDATIONS. INSTALL PRESSURE PLATES WHEREPOSSIBLE.JUST BEFORE INSTALLING VERTICAL PRESSUREPLATES APPLY A GENEROUS AMOUNT OFSEALANT TO THE JOINT PLUG FACE FILLINGJOINTS AS SHOWN.CLEAN JOINT PER SEALANTMANUFACTURER'S RECOMMENDATIONS5) REPLACE LOCKING PLATE INTO NOTCHES AND INSTALLSNAP RING. IF LOCKING PLATE DOES NOT "SEAT", MOVETHE ADJUSTING NUT SLIGHTLY UNTIL IT DROPS IN PLACE.THE DIRECTION IS BEST DETERMINED BY WHETHER AMINIMUM TORQUE APPLICATION OR A MAXIMUM ONE ISDESIRED.A-ASIDE BLOCK027855 (1" GLASS)027856 (1/4" GLASS)SPANDRELGLASSFACE VIEWA-AB-B5SPANDRELGLASS23REMOVE EXCESSIVESEALANT FROM ALLGLASS CORNERSTO PROVIDE WATERDRAINAGE1BB4INSTALL PRESSURE PLATES USING SCREWS 128406 1/4-14 X 1"HEX WASHER HEAD TYPE AB.027855VISIONGLASS027856INSTALL SIDE BLOCKS, COMPRESSING AS SHOWNSCREWS ARE TO BE LOCATED 9" ON CENTER.ALWAYS LOCATE A SCREW AS CLOSE AS POSSIBLE TO AHORIZONTAL JOINT. THIS WILL PROVIDE MAXIMUM PRESSUREFOR THE CRITICAL JOINT SEALS.INSTALL HORIZONTAL PRESSURE PLATES WITH WEEP HOLESTOWARDS TOP OF HORIZONTAL.AT EACH HORIZONTAL AND VERTICAL PRESSURE PLATEINSTALL TWO SCREWS PART WAY, THEN INSTALL THE THIRDSCREW ALL THE WAY, AND THEN TIGHTEN THE FIRST TWOSCREWS. THIS ELIMINATES LATERAL WALKING OF THEPRESSURE PLATE POSITION.VISIONGLASSSPANDRELGLASSTORQUE ALL SCREWS TO 95 TO 100 INCH POUNDS. DURINGCOLD WEATHER, TORQUE SCREWS TO 50 INCH POUNDSUNTIL ALL 4 SIDES HAVE BEEN CLAMPED. THEN TORQUESCREWS TO 95 TO 100 INCH POUNDS.SPANDRELGLASSB-BCURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 07 OF 09

162970 SHEET 08 OF 09STEP 17 - INSTALL EXTERIORPRESSURE PLATESINSTALL HORIZONTAL PRESSURE PLATESINSTALL VERTICAL PRESSURE PLATESNOTE - THE TORQUE LIMIT TOOL WAS DESIGNEDTO BE USED WITH A HAND DRIVEN DEVICE.THE TOOL CAN BE ADAPTED TO A DRILL MOTORIF USED AT A MAXIMUM SPEED OF APPROXAMITTLY300 RPM. HIGHER SPEEDS CAN CAUSE OVERHEATINGAND AFFECT THE ACCURACY. AFTER APPROXAMITTLY1 HOUR OF TOOL USAGE CHECK TORQUE SETTINGSWITH A TORQUE WRENCH.INTERMEDIATEHORIZONTALVISION OVERSPANDRELABDESEAL JOINTS ASSHOWN. TOOLSEALANT. THISSEAL IS TO JOINAND ADHERE TOTHE JOINT PLUGSEALSGASKET027850VERTICAL GASKETSTOPS 1" SHORTAT HEAD AND SILLCONDITIONSAT TOP PRESSURE PLATELOCATE SCREW CLOSE TOTHE MULLION JOINT BUTNOT BELOW THE JOINTCECCLEAN JOINT PERSEALANTMANUFACTURER'SRECOMMENDATIONSA-AHEAD CONDITIONSILL SAMEHEAD HORIZONTALSILL SAMEDBTOOL EXCESSSEALANTSEAL BETWEEN PRESSUREPLATE AND HEAD/SILL ENDCAP AS SHOWN.ATOP OF VERTICALMULLION TO TOPOF PRESSUREPLATE IS 1-1/2"INTERMEDIATE HORIZONTALVISION OVER SPANDRELREFERENCE INSTRUCTIONS 162983FOR EXTERIOR FRAME PERIMETERSCENTER HORIZONTAL PRESSURE PLATESSO END GAPS ARE EQUAL.VERTICAL EXPANSION JOINTSINSTALL VERTICAL PRESSURE PLATESDO NOT LET THE SEAL INTERFEREWITH THE COVER SNAPD-DSEAL JOINTS ASSHOWN. TOOLSEALANT. THISSEAL IS TO JOINAND ADHERE TOTHE JOINT PLUGSEALS.CLEAN JOINTPER SEALANTMANUFACTURER'SRECOMMENDATIONSDO NOT LET THE SEAL INTERFEREWITH THE COVER SNAPVERTICAL GASKETSTOPS 1"SHORT OF ENDGASKET027857GASKET027850B-BCLEAN JOINTPER 0TOOL EXCESSSEALANTGASKET027850FACE VIEWGASKET027850FACE VIEWPERIMETER FILLERHEAD CONDITIONSILL SAMEPERIMETER FILLERVERTICAL GASKETSTOPS 1" SHORTAT HEAD AND SILLCONDITIONSDO NOT LET THE SEAL INTERFEREWITH THE COVER SNAPHEAD HORIZONTALSILL SAMEDC-CDGASKET027850ECOMPLETELY SEAL JOINT.DO NOT LET SEALANTINTERFERE WITH COVERSNAP. OVERLAP PRESSUREPLATE FACE CREATINGA BAND-AID SEAL.TOOL EXCESSSEALANTCECSEAL JOINTS ASSHOWN. TOOL SEALANT.THIS SEAL IS TO JOINAND ADHERE TO THEJOINT PLUG SEALS.CURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 08 OF 09

162970 SHEET 09 OF 09STEP 18 - INSTALL PERIMETERWEATHER SEALSSTEP 19 - INSTALL EXTERIOR COVERSPERIMETER WEATHER SEALS ARE INSTALLED AT THEPRESSURE PLATE LOCATION AS DETAILED BELOW.(THIS SEAL SHOULD BE INSTALLED BEFORE COVERSARE APPLIED WHEN COVERS DEEPER THAN 3/4" AREUSED) EXTERIOR COSMETIC SEALS AT THE COVERMAY BE APPLIED AT THE HEAD, JAMB AND SILL.COSMETIC SEAL AT SILL COVERS MUST ALL WATERDRAINAGE TO THE EXTERIOR.CARE MUST BE TAKEN TO AVOID DAMAGETO COVERS DURING INSTALLATION. USEA 18" LONG PIECE OF 2" X 4" WOOD ALONGWITH A HAMMER OR MALLET TO SEATTHE COVER.STEP 19 - INSTALL EXTERIOR COVERSPINNING OF ALL VERTICAL COVERS IS REQUIRED FOR BOTHSIDES. DRILL A 0.106 DIA. HOLE (#36 DRILL) AND INSTALL128920 SCREWS #6 X 3/8" PAN HEAD TYPE B. LOCATE PINNINGAT A HORIZONTAL CLOSEST TO THE COVER HEIGHT CENTER.(ONE SIDE ONLY AT JAMBS)REMOVING COVERSCOVERS CAN BE SAVED IF TOLERANCES ARENOT TOO TIGHT AND THE COVER IS REMOVEDWITH EXTREME CAREWOOD ORPLASTICSHIMPRY BAR WITH SHARPPOINT AND FLAT THIS SIDEREQUIREDWEATHERSEALOPTIONALCOSMETICSEALPUSH BACK THE GASKETTRIM LIP START AT ONEEND TO DISENGAGE DOTHIS IN PROGRESSIONFOR THE COMPLETELENGTHHEADCONDITIONENGAGE ONESIDE OF COVERAS SHOWNCOVERDEPTHDO NOTSEAL OVERWEEP HOLES128920#6 SCREWS5/16"OPTIONALCOSMETICSEALNOTE FOR 5" SIGHTLINE COVERSDUE TO LARGE EXTRUSION TOLERANCES, 5" SIGHTLINECOVERS MAY REQUIRE SEALANT OR PINNING TO HOLDIN PLACE.2" X 4" WOOD18" LONGSILLCONDITIONHAMMER ORMALLETINSTALL HORIZONTAL COVERS WITHTHE WEEP HOLES DOWNWEEP LEXPANSIONJOINTEQUAL SPACEBOTH ENDS OFHORIZONTALCOVER1/32"TOP OF PRESSUREPLATE TOOF COVERIS NDITIONHORIZONTAL COVERGREATER THAN1-1/4" PROJECTION9/16"REQUIREDWEATHERSEAL128920#6 SCREWSOPTIONALCOSMETICSEALSPLICE SLEEVEIS FACTORYAPPLIED TOBOTTOM COVERDEEP COVERPRESSUREPLATEFOR HORIZONTAL COVERSWITH A PROJECTIONDEEPER THAN 1-1/4"THE COVERS ARE TO BEPINNED AS SHOWN AT THECENTER OF THE COVER WIDTHCURTAIN WALLINSTALLATIONProduct Engineering & Development INSTRUCTIONS95449-11504/21/17162970 SHEET 09 OF 09

kawneer company inc. these drawings are the sole and exclusive property of kawneer and contain sensitive, privileged or confidential information which may be used only for its . use part 162316 for the 6" deep system use part 162317 for the 7 1/2" deep system open back horizontals 7 1' &251(56 whenever possible avoid using open back horizontals