Mass TransitPROGRAM DESCRIPTION AND OBJECTIVESProjects in this program are intended to enhance mobility by providing convenient and affordable mass transit alternatives to singleoccupancy vehicle travel and to reduce traffic congestion and vehicle emissions.The County's Mass Transit/WMATA Capital Program provides an essential alternative to single occupant vehicle travel andcontributes to the reduction of traffic congestion. The goal of the County's Mass Transit/WMATA Capital Program is to provideinfrastructure, equipment, and supporting facilities for the operation of safe, reliable, convenient, and affordable public transportationsystems to the residents of Montgomery County. The infrastructure, equipment, and supporting facilities for these transit systemsmust be constructed, maintained, rehabilitated, and replaced to ensure safety and operational effectiveness.HIGHLIGHTSAdd funding for full design, land acquisition, and construction of MD 355 Bus Rapid Transit (BRT) Central phase, withcompletion in FY28.Add funding to complete full design of MD 355 Bus Rapid Transit (BRT) South/North phase.Add funding for full design, land acquisition, and construction of Veirs Mill Road Bus Rapid Transit (BRT) with completion inFY27.Add funding in the Bus Priority Project to enhance countywide bus system performance.Continue planning for the New Hampshire Avenue Bus Rapid Transit (BRT) corridor and the North Bethesda Transitway.Continue design and construction of the Great Seneca Science Corridor Transit Improvements.Replace 29 diesel Ride On buses with zero emission electric models in fiscal years 2023-24 to achieve full capacity of 70 electricbuses at the Silver Spring bus depot solar microgrid by FY25.Add funding to support the construction of a mezzanine for the south entrance of the Bethesda Metrorail Station incoordination with the Purple Line project.Provide oversight and financial support for the Purple Line project which will provide significant economic and mobilitybenefits.Continue efforts to improve the condition of Ride On bus stops.Design and construct a new bus loop and parking lot at the Boyds MARC Station.Complete access improvements to the White Flint Metro Station.PROGRAM CONTACTSContact Brady Goldsmith of the Department of Transportation at 240.777.2793, or Gary Nalven of the Office of Management andBudget at 240.777.2779 for more information regarding this department's capital budget.CAPITAL PROGRAM REVIEWMass Transit (MCG)16-1

The FY23-28 Mass Transit/WMATA component of the Transportation capital budget includes 17 active projects. The program totals 655.0 million over the six year period. This represents an increase of 373.3 million or 133 percent from the 281.7 million in theAmended FY21-26 program. This increase is largely due to the addition of two large Bus Rapid Transit (BRT) projects to beconstructed on MD 355 and MD 586 (Veirs Mill Road), which primarily utilize non-county funding, as well as a significant increase inRide On bus replacement costs to reflect the transition to a zero emissions bus fleet.STATE TRANSIT PROGRAM/PURPLE LINEIn addition to transit projects programmed by Montgomery County, the Maryland Transit Administration (MTA) develops andprovides transit services within the County on the Brunswick MARC rail line from Brunswick to Silver Spring, providing a convenientconnection to the Washington regional Metrorail system.The State's Draft Consolidated Transportation Program (CTP) is released each October. Final action on the Statewide CTP is taken bythe General Assembly. The County continues to work with the State and the Concessionaire under a Public Private Partnership (PPP)for the 16-mile Purple Line light rail project. In addition to completing the design and construction of the project, the Concessionairewill operate and maintain the light rail corridor for a period of 30 years.The Purple Line project is included to provide oversight and financial support to this State project. As with any large infrastructureproject, significant impacts to the community - both residents and business along the corridor - are anticipated during the constructionperiod. The County is actively engaged with the community throughout the various project stages. The County is also providingtechnical review and oversight of both the County-funded projects (Bethesda Metro Station South Entrance, Silver Spring Green Trail,and Capital Crescent Trail) and the overall Purple Line project to ensure that they are in keeping with County standards.BUS RAPID TRANSITMCDOT continues to advance FLASH Bus Rapid Transit (BRT) to deliver a new high-quality, high-capacity transit option in thecounty. Making efficient use of existing roadways, FLASH will provide a more robust and reliable system that will increase transitridership. Design, land acquisition, and/or construction of projects are funded on three BRT corridors from the adopted CountywideTransit Corridors Functional Master Plan - MD 355, MD 586 (Veirs Mill Road), and US 29. Leveraging anticipated federal aid andpledged toll revenues from the State's Op Lanes Maryland Project, MCDOT will add median dedicated bus lanes and construct levelboarding platforms, intersection queue jumps, and other system improvements to provide FLASH service on zero-emission BRTbuses from Rockville to Germantown on MD 355. BRT will also be implemented on Veirs Mill Road through a combination of somededicated shoulder bus lanes and other improvements, connecting to MD 355 in Rockville to expand the FLASH in the central part ofthe County from Wheaton to Rockville. In addition, bicycle and pedestrian improvements associated with the Veirs Mill and RandolphRoad Bicycle & Pedestrian Priority Areas (BiPPA) are being accelerated to further increase access to FLASH stations while improvingpedestrian and bicycle safety along the Veirs Mill Road corridor. MCDOT will continue engineering for the entire MD 355 transitcorridor to eventually extend FLASH service south to Bethesda and north to Clarksburg.The US29 FLASH line has completed construction and began operation in 2020, with planning and design underway to add morededicated bus lanes. Planning for the North Bethesda Transitway and New Hampshire Avenue BRT corridors began in FY22 and willbe completed in FY23 and FY24, respectively.Mass Transit (MCG)16-2

Bethesda Metro Station South Entrance(P500929)CategoryTransportationDate Last Modified01/11/22SubCategoryMass Transit (MCG)Administering AgencyTransportationPlanning AreaBethesda-Chevy Chase and VicinityStatusUnder ConstructionEXPENDITURE SCHEDULE( 000s)Total6 YearsFY 23FY 0006,0006,000------TOTAL EXPENDITURES 130,20255,07835,380 39,744 12,980 24,111 2,63221---FY 25 FY 26 FY 27 FY 28Beyond6 YearsCost ElementsTotal Thru FY21 Est FY22Planning, Design and Supervision1,9191,75629LandSite Improvements and UtilitiesConstructionOtherFUNDING SCHEDULEFunding SourceG.O. BondsTotal Thru FY21 Est FY22FY 25 FY 26 FY 27 FY 28Beyond6 Years( 000s)Total6 YearsFY 23FY ,1596,159---------12,99212,992---------TOTAL FUNDING SOURCES 130,20255,07835,380 39,744 12,980 24,111 2,63221---Impact TaxRevenue Bonds: Liquor FundAPPROPRIATION AND EXPENDITURE DATA( 000s)Appropriation FY 23 Request1,334Year First AppropriationFY09Appropriation FY 24 Request24,111Last FY's Cost Estimate110,202Cumulative Appropriation102,104Expenditure / Encumbrances63,870Unencumbered Balance38,234PROJECT DESCRIPTIONThis project provides access from Elm Street west of Wisconsin Avenue to the southern end of the Bethesda Metrorail station andultimately integrates the Metro system with the new light rail system, allowing the completion of the connection between the newPurple Line light rail system and the existing Metrorail Red Line. The Metrorail Red Line runs below Wisconsin Avenue throughBethesda more than 120 feet below the surface, considerably deeper than the Purple Line right-of-way. The Bethesda Metrorail stationhas one entrance, near East West Highway. The Metrorail station was built with accommodations for a future southern entrance. TheBethesda light rail transit (LRT) station would have platforms located just west of Wisconsin Avenue on the Georgetown Branch rightof-way. This platform allows a direct connection between LRT and Metrorail, making transfers as convenient as possible. Six stationelevators would be located in the Elm Street right-of-way, which would require narrowing the street and extending the sidewalk. TheMass Transit (MCG)16-3

station would include a new south entrance to the Metrorail station, including a new mezzanine above the Metrorail platform, similarto the existing mezzanine at the present station's north end. The mezzanine would use the existing knock-out panel in the arch of thestation and the passageway that was partially excavated when the station was built in anticipation of the future construction of a southentrance.ESTIMATED SCHEDULEConstruction started in FY18. Construction will be coordinated and implemented as part of the State Purple Line Project and will becompleted when the Purple Line construction is complete. In FY21, the schedule was revised again based on actual progress andMTA's latest revised cash flow projection.COST CHANGECost increase due to revised estimate for mezzanine construction. See explanation in Fiscal Note.OTHERPart of Elm Street west of Wisconsin Avenue will be closed for a period during construction.FISCAL NOTEThe funds for this project were initially programmed in the State Transportation Participation project. Appropriation of 5 million fordesign was transferred from the State Transportation Participation project in FY09. In FY18, a funding switch was made to increaseRevenue Bonds: Liquor Fund appropriation and decrease GO Bonds appropriation by 7.992 million. In FY19, a shift in 3.5 millionin GO Bonds from FY21 to FY19 was done to reflect an updated MTA billing schedule. In FY21, 29,374,000 was shifted from prioryears and distributed across FY21-FY26 to further reflect actual progress, a new estimated billing schedule, and to account for delaysassociated with the Purple Line. In the FY23-FY28 CIP, 20 million was added to fill a funding gap in the project to allow for thecompletion of the Bethesda South Metro Entrance mezzanine project element as planned.COORDINATIONMaryland Transit Administration, Washington Metropolitan Area Transit Authority (WMATA), Maryland-National Capital Parkand Planning Commission, Bethesda Lot 31 Parking Garage project, Department of Transportation, Department of General Services,Special Capital Projects Legislation [Bill No. 31-14] was adopted by Council June 17, 2014.Mass Transit (MCG)16-4

Mass Transit (MCG)16-5

Boyds Transit Center(P501915)CategoryTransportationDate Last Modified12/22/21SubCategoryMass Transit (MCG)Administering AgencyTransportationPlanning AreaGermantown and VicinityStatusPreliminary Design StageEXPENDITURE SCHEDULE( 000s)Cost ElementsTotalThru FY21Est FY22Total6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond6 YearsPlanning, Design and 1,0983,8513073,544-----LandSite Improvements and UtilitiesConstructionTOTAL EXPENDITURESFUNDING SCHEDULEFunding SourceContributionsG.O. BondsTOTAL FUNDING SOURCES( 000s)TotalThru FY21Est FY22Total6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond6 ,6507011,0983,8513073,544-----OPERATING BUDGET IMPACTImpact TypeTotalThru FY21Est FY22MaintenanceEnergyNET IMPACT( 000s)BeyondFY 286 YearsTotal6 YearsFY 23FY 24FY 25FY 26FY 2720--55554--111124--6666APPROPRIATION AND EXPENDITURE DATA( 000s)Appropriation FY 23 Request3,444Year First AppropriationFY19Appropriation FY 24 Request-Last FY's Cost Estimate5,650Cumulative Appropriation2,206Expenditure / Encumbrances736Unencumbered Balance1,470PROJECT DESCRIPTIONThis project provides the site remediation followed by design and construction for a new bus loop and parking lot on the formerAnderson property at the Boyds MARC station.Mass Transit (MCG)16-6

LOCATION15100 Barnesville Road, BoydsESTIMATED SCHEDULEThe site remediation was completed in FY22. Design for the bus loop and parking lot will begin in FY22 with construction completionin FY24.PROJECT JUSTIFICATIONAs part of its facility planning process, the County has been working towards the preliminary design of a future transit center in closeproximity to the Boyds MARC station. The existing station is popular among commuters but parking is limited. In addition, providingRide-On bus service to the station is difficult due to the road network and lack of space for buses to turn around. In the Summer of2017, the County learned that the owners of the property adjacent to the MARC station (the Anderson Family) had listed theproperty for sale. In FY19, the County purchased the property. The County's acquisition of the Anderson property is supported bythe Boyds Civic Association and the Maryland-National Capital Park & Planning Commission. As the design of the transit stationcontinues to develop, the County intends to seek participation from the State of Maryland.FISCAL NOTEThe contribution amount was reduced based on the actual cost that was less than the budgeted site remediation cost.DISCLOSURESA pedestrian impact analysis has been completed for this project.COORDINATIONMaryland Transit Administration, CSX Transportation, Historic Preservation Program of Maryland National Capital Park andPlanning Commission, Department of Permitting Services.Mass Transit (MCG)16-7

Mass Transit (MCG)16-8

Burtonsville Park and Ride Improvements(P502203)CategoryTransportationDate Last Modified01/07/22SubCategoryMass Transit (MCG)Administering AgencyTransportationPlanning AreaFairland-Beltsville and VicinityStatusPlanning StageEXPENDITURE SCHEDULECost ElementsPlanning, Design and SupervisionTOTAL EXPENDITURESTotalThru FY21Est FY22Total6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond6 Years500-500--------500-500--------FUNDING SCHEDULEFunding SourceState AidTOTAL FUNDING SOURCES( 000s)( 000s)TotalThru FY21Est FY22Total6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond6 Years500-500--------500-500--------APPROPRIATION AND EXPENDITURE DATA( 000s)Appropriation FY 23 Request-Year First AppropriationFY22Appropriation FY 24 Request-Last FY's Cost Estimate500Cumulative Appropriation500Expenditure / Encumbrances-Unencumbered Balance500PROJECT DESCRIPTIONState aid will fund a feasibility study for constructing a parking garage or other improvements at the Burtonsville Park and Ride Lot insupport of FLASH service on the US 29 corridor and to facilitate reactivation or redevelopment of the adjacent commercial property.Planning for the access and egress routes to the park-and-ride may also include advancing the concept for a road diet on Old ColumbiaPike between the Burtonsville Crossing Shopping Center and the Burtonsville Town Center Shopping Center to better link thesecommercial properties, reduce impervious area, and improve safety. The Burtonsville Station is the northernmost FLASH station inMontgomery County and is well-situated for park-and-ride access with direct ramps to US 29 and strong east-west connections viaMaryland 198. With this strategic location, the park-and-ride can serve residents of Montgomery, Prince George's and Howard County,increasing transit ridership and lowering traffic demands on US 29 through Montgomery County. Expansion of this park-and-ride isneeded to accommodate future ridership at this station and is part of longer-term plans to extend FLASH service into Howard Countyand to provide all-day service in Burtonsville. The location can also serve as a hub for interconnecting local services to nearbycommunities like Cloverly, Ashton, Laurel and Maple Lawn. Expansion of public parking capacity at this location may also facilitate amore compelling development vision for County, State and privately owned properties in this part of Burtonsville.ESTIMATED SCHEDULEMass Transit (MCG)16-9

The feasibility study is expected to be completed in FY22 and is being coordinated with the development RFP.PROJECT JUSTIFICATIONIt is estimated that by 2040 there will be a need for 1,000 park-and-ride spaces at the Burtonsville Park-and-Ride to serve the FLASHservice and the current capacity of the park-and-ride lot is only 475 spaces. This parking also serves Metrobus and MTA bus servicesand supports County employee commuting. The park and ride lot has strong access to US 29, but access from Old Columbia Pike andMaryland 198 relies upon connections through adjacent commercial development. The Burtonsville Crossing Shopping Center isimmediately adjacent to the park-and-ride lot and the rear of the center faces the FLASH station. The Burtonsville Crossing ShoppingCenter has struggled to retain and attract tenants since the opening of the Burtonsville Town Center, directly across Old Columbia Pike,and the completion of the Burtonsville overpass on US 29. The center is currently home to only two small businesses on a 16 acre site.With such low occupancy, the shopping center has become a source of community concern. Reconfiguration of the park-and-ride lotand its access routes, may be an important element of reactivating or redeveloping the Burtonsville Crossing Shopping Center andbetter integrating development on the approximately 36 acres of land between Old Columbia Pike, US 29, Maryland 198 and thePepco transmission lines.FISCAL NOTEDGS issued an RFP for development of the site in FY21, with responses expected in FY22. An additional 4.5 million in State Aid isavailable to begin implementation of recommendations from the feasibility study and will be coordinated with joint developmentefforts.DISCLOSURESA pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this projectconforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and PlanningAct.COORDINATIONGeneral Services, Intergovernmental Relations, Office of the County Executive, Community Engagement Cluster.Mass Transit (MCG)16-10

Bus Priority Program - Minor Projects(P502204)CategoryTransportationDate Last Modified01/09/22SubCategoryMass Transit (MCG)Administering AgencyTransportationPlanning AreaCountywideStatusOngoingEXPENDITURE SCHEDULETotalFY 23 FY 246 YearsFY 25FY 26FY 27FY 28Beyond6 0720720-5,0005005001,0001,0001,0001,000-FY 25FY 26FY 27FY 28Beyond6 YearsCost ElementsTotalThru FY21Est FY22Planning, Design and 0-1,250Site Improvements and UtilitiesConstructionTOTAL EXPENDITURES( 000s)FUNDING SCHEDULE( 000s)TotalFY 23 FY 246 YearsFunding SourceTotalThru FY21Est FY22Current Revenue: Mass 6,250-1,2505,0005005001,0001,0001,0001,000-TOTAL FUNDING SOURCESAPPROPRIATION AND EXPENDITURE DATA( 000s)Appropriation FY 23 Request500Year First AppropriationFY22Appropriation FY 24 Request500Last FY's Cost Estimate1,250Cumulative Appropriation1,250Expenditure / Encumbrances-Unencumbered Balance1,250PROJECT DESCRIPTIONThis program provides for the planning, design, and construction of improvements such as bus lanes; queue jumps; passenger boardingand alighting improvements; implementation of transit signal priority; enhanced bus stops; and other similar capital improvements thatwill result in improved bus operations throughout Montgomery County. These improvements will advance the transit networkspecified by master plans. Potential improvements may also be identified through other planning and transit operations studies orrequested by community members.ESTIMATED SCHEDULEProjects programmed for FY22 include: Veirs Mill Road, near the Wheaton Metrorail Station; Century Boulevard, Crystal Rock Driveand Aircraft Road near the Germantown Transit Center; and US 29 in Silver Spring. FY23 projects will be coordinated with theWashington Metropolitan Area Transit Authority's Bus Priority Program, which will provide design for bus reliability improvementsfor up to two corridors in Montgomery County, with the intention that the improvements would be implemented by the County.Mass Transit (MCG)16-11

COST CHANGEAddition of 5 million over the six years will fund an ongoing level of effort for transit service improvements.PROJECT JUSTIFICATIONMontgomery County is working towards implementation of a 102-mile bus rapid transit (BRT) network that will dramaticallyimprove transit and support the county's economic development, equity, and environmental goals. This network is focused on tenprimary corridors within Montgomery County and is an ambitious plan to improve bus transit service and refocus how people travelin Montgomery County. Individual corridor projects are complex, costly, and take several years to implement. Recognizing theimportance of improving bus performance in the shorter term, the Montgomery County Department of Transportation is advancingthe Bus Priority Program to provide targeted and quickly implementable improvements that will result in improved bus reliability andtravel time.DISCLOSURESA pedestrian impact analysis will be performed during design or is in progress. Expenditures will continue indefinitely.COORDINATIONMaryland Department of Transportation, Washington Metropolitan Area Transit Authority, Maryland-National Capital Park andPlanning Commission, City of Rockville, City of Gaithersburg, State Highway AdministrationMass Transit (MCG)16-12

Bus Rapid Transit: MD 355 Central(P502005)CategoryTransportationDate Last Modified01/11/22SubCategoryMass Transit (MCG)Administering AgencyTransportationPlanning AreaCountywideStatusPreliminary Design StageEXPENDITURE SCHEDULETotalThruFY21EstFY22Total6 YearsPlanning, Design and -77,800Site Improvements and Utilities27,100--137,100-21,000-TOTAL EXPENDITURES 314,3702,111Cost ElementsConstructionOtherFY 25FY 26FY 27FY 28Beyond6 050,00018,500--21,000----10,00011,000-9,389 302,870 10,700 8,200 50,230 117,090 84,640 32,010-FY 23 FY 24FUNDING SCHEDULEFunding SourceCurrent Revenue: Mass Transit( 000s)TotalThruFY21EstFY22Total6 Years( 000s)FY 23 FY 24FY 25FY 26FY 27FY 28Beyond6 Years6,750-7506,000-----6,000-Federal ct 22,10151,52037,2428,244-Recordation Tax Premium (MCG)8,1861,1863,0004,0004,000------State Aid6,000-3,5002,5002,500------TOTAL FUNDING SOURCES 314,3702,1119,389 302,870 10,700 8,200 50,230 117,090 84,640 32,010-Op Lanes Maryland Transit FundingAPPROPRIATION AND EXPENDITURE DATA( 000s)Appropriation FY 23 Request7,200Year First AppropriationFY20Appropriation FY 24 Request8,200Last FY's Cost Estimate24,000Cumulative Appropriation15,000Expenditure / Encumbrances4,667Unencumbered Balance10,333PROJECT DESCRIPTIONThis project will design and construct a new Bus Rapid Transit (BRT) line on MD 355 between Rockville and Germantown fromMontgomery College - Rockville to Montgomery College - Germantown. The project includes dedicated BRT lanes, new BRT stationswith level boarding and off-board payment, Transit Signal Priority (TSP), purchase of new zero-emission BRT buses, and otherassociated pedestrian and bicycle improvements along the corridor. Planning conducted by the Maryland Department ofTransportation Maryland Transit Administration (MDOT MTA) resulted in several alternatives retained for detailed study in 2017Mass Transit (MCG)16-13

for BRT along MD 355 from Bethesda to Clarksburg. In 2019, MCDOT completed the planning phase. MCDOT has been workingon preliminary engineering and project phasing since 2020. Preliminary engineering of the full corridor from Bethesda to Clarksburg isbeing completed and then final design and construction for the Central segment will occur. Final design and construction of the Northand South segments will occur as a separate project.LOCATIONThe MD 355 BRT corridor spans Clarksburg to Bethesda. The Central phase of this project will include the master plan areas ofShady Grove and Germantown, as well as the cities of Rockville and Gaithersburg. A subsequent phase will provide service to themaster plan areas of Bethesda, North Bethesda, Garrett Park, White Flint and Clarksburg.ESTIMATED SCHEDULEProject planning was completed in FY19. Preliminary engineering began in FY20 and will be completed in FY23. Final design willimmediately follow and will be completed in FY25. Construction activities, including right of way acquisition, will begin in FY25.Construction will be completed in FY28.COST CHANGEIncreased funding to complete final design of the Central phase from Rockville to Germantown, acquire right of way, relocate utilities,complete construction, and purchase buses.PROJECT JUSTIFICATIONMD 355 FLASH will transform mobility options with the implementation of a 22-mile, premium, branded, limited-stop BRT servicealong MD 355 between Clarksburg and Bethesda. This new service will improve transit travel time and increase opportunity for abroad range of users along a highly congested corridor. MD 355 FLASH will improve passenger transit mobility by connecting riders tohigh density housing and employment centers. MD 355 FLASH is being phased to accelerate delivery. This phase will implementBRT between Rockville and Germantown. Extensions to Bethesda and Clarksburg will follow.FISCAL NOTEProgramming of funds through final design and construction improves the project's eligibility for earlier entry into the Federal TransitAdministration's Capital Investment Grant program. This project will utilize Op Lanes Maryland revenue proceeds, which have beenpledged by the Maryland Department of Transportation to fund high priority public transit projects in Montgomery County.DISCLOSURESA pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this projectconforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and PlanningAct.COORDINATIONMaryland-National Capital Park and Planning Commission (M-NCPPC), Maryland DOT State Highway Administration &Maryland Transit Administration, Department of Environmental Protection, Department of Permitting Services, Washington Gas,Pepco, Verizon, Comcast, Maryland Department of Natural Resources, Federal Transit Administration, City of Gaithersburg, City ofMass Transit (MCG)16-14

Rockville, Washington Metropolitan Area Transit Authority, Commission on People with Disabilities, Transit Advisory Group,Neighborhood and Civic Associations, MD 355 BRT Corridor Advisory CommitteeMass Transit (MCG)16-15

Mass Transit (MCG)16-16

Bus Rapid Transit: MD 355 South/North(P502309)CategoryTransportationDate Last Modified01/09/22SubCategoryMass Transit (MCG)Administering AgencyTransportationPlanning AreaCountywideStatusPreliminary Design StageEXPENDITURE SCHEDULE( 000s)Cost ElementsTotalThru FY21Est FY22Total6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond6 YearsPlanning, Design and 4,8504,850-----TOTAL EXPENDITURESFUNDING SCHEDULE( 000s)Funding SourceTotalThru FY21Est FY22Total6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond6 YearsOp Lanes Maryland Transit Funding9,700--9,7004,8504,850-----TOTAL FUNDING SOURCES9,700--9,7004,8504,850-----APPROPRIATION AND EXPENDITURE DATA( 000s)Appropriation FY 23 Request4,850Year First AppropriationFY23Appropriation FY 24 Request4,850Last FY's Cost Estimate-Cumulative Appropriation-Expenditure / Encumbrances-Unencumbered Balance-PROJECT DESCRIPTIONThis project will complete design for the Southern and Northern segments of the MD 355 Bus Rapid Transit (BRT) corridor. TheSouthern segment is from Montgomery College - Rockville to Bethesda Metro station. The Northern segment is from MontgomeryCollege - Germantown to Clarksburg. This is part of the larger MD 355 BRT corridor that extends from Bethesda to Clarksburg. TheCentral segment will be designed and constructed as a separate project. Planning conducted by the Maryland Department ofTransportation Maryland Transit Administration (MDOT MTA) resulted in several alternatives retained for detailed study in 2017. In2019, MCDOT completed the planning phase. MCDOT has been working on preliminary engineering and project phasing since 2020.The project includes dedicated BRT lanes, new BRT stations with level boarding and off-board payment, Transit Signal Priority (TSP),purchase of new zero-emission BRT buses, and other associated pedestrian and bicycle improvements along the corridor. Preliminaryengineering of the project is currently being completed.LOCATIONMD 355 between Rockville and Bethesda in the south and Germantown and Clarksburg in the north. Master plan areas include:Bethesda, North Bethesda, Garrett Park, White Flint, Germantown, and Clarksburg. The project also includes the city of Rockville.Mass Transit (MCG)16-17

ESTIMATED SCHEDULEPreliminary engineering will be completed in FY23 (see fiscal note). Final design will begin in FY24 and complete in FY25. Theconstruction schedule is unknown at this time.PROJECT JUSTIFICATIONThe project will transform mobility options with the completed implementation of a 22-mile, premium, branded, limited-stop BRTservice along MD 355 between Clarksburg and Bethesda. This new service will improve transit travel time and increase opportunityfor a broad range of users along a highly congested corridor. The project will improve passenger transit mobility by connecting riders tohigh density housing

The County's Mass Transit/WMATA Capital Program provides an essential alternative to single occupant vehicle travel and contributes to the reduction of traffic congestion. The goal of the County's Mass Transit/WMATA Capital Program is to provide infrastructure, equipment, and supporting facilities for the operation of safe, reliable, convenient .