Seattle Public Schools Building Excellence IV Projects .

Transcription

Seattle Public Schools Building Excellence IVProjects Under ConstructionProjectSlide NumberArbor Heights Elementary School2Genesee Hill Elementary School13Hazel Wolf K-8 at Pinehurst24New Thornton Creek Building35September 25, 2015

Arbor Heights Elementary SchoolElementarySchoolInterior and exterior light-gauge metal framing is ongoing at SouthBuilding. Installation of hollow-metal door frames in-progress at 1st floor SouthBuilding. Mechanical, electrical, plumbing layout and installation is ongoing atSouth Building. Metal pan-decking stud and mesh installation at North and South Buildingin-progress.

Arbor Heights Elementary SchoolSite PlanJuly 1, 2015July 10, 2015

Arbor Heights Elementary SchoolAerial view from the SouthSeptember 2, 2015

Arbor Heights Elementary SchoolSouth Building 1st Floor View from West looking EastSeptember 22, 2015

Arbor Heights Elementary SchoolSouth Building 1st Floor Framing Rough-InSeptember 22, 2015

Arbor Heights Elementary SchoolSouth Building 1st Floor Rough-in BoxesSeptember 22, 2015

Arbor Heights Elementary SchoolSouth Building 3rd Floor Pipe Penetration Pan-DeckingSeptember 22, 2015

Arbor Heights Elementary SchoolNorth Building Pier Footing InstallationSeptember 22, 2015

Arbor Heights Elementary SchoolNorth Building Installing Footing Drains and DownspoutsSeptember 22, 2015

Arbor Heights Elementary SchoolNorth Building Steel Beams at StairwellSeptember 22, 2015

Arbor Heights Elementary SchoolNorth Building 2nd Floor Nelson Studs in Pan-DeckingSeptember 22, 2015

Genesee Hill Elementary School Area 1: Began spray foam insulation at exterior walls, air barrier installationongoing; continued installation of CMU veneer; continued installation offire sprinkler mains; duct insulation ongoing; plumbing and electricalrough-in is ongoing. Area 2: Moment welds complete; roof block nearing completion; level 2slab-on-deck pour complete; electrical rough-in at level 2 ongoing. Area 3: Installation of exterior brick ledger continues; installation of airbarrier ongoing; electrical rough in progressing. Area 4: Seattle Glass pre-fabricating windows for area 1; installation ofmetal decking on covered walkway at roof. Site: Excavating for future sewer boring.

Genesee HillElementary SchoolSite Plan4

Genesee Hill Elementary SchoolAerial View

Genesee Hill Elementary SchoolArea 1 CMU Veneer and Air Barrier Installation

Genesee Hill Elementary SchoolArea 1 Level 1 Interior Framing

Genesee Hill Elementary SchoolArea 1 Level 2 Spray Foam Insulation Install

Genesee Hill Elementary SchoolArea 1 Level 3 Electrical and Plumbing Rough-In

Genesee Hill Elementary SchoolArea 2, Level 2 Pouring Concrete Slab-on-Deck

Genesee Hill Elementary SchoolArea 3 Air Barrier Installation

Genesee Hill Elementary SchoolArea 3 Level 1 Electrical Rough-In

Genesee Hill Elementary SchoolArea 4 Covered Walkway Metal Deck Installation

Hazel Wolf K-8 at Pinehurst Metal decking installation was started on the kitchen/library building wingand decking on the classroom building was completed. Structural steelerection continued on the day care/gymnasium area and welding andbolting continued on the library/kitchen areas. Steel continued to bedelivered on site this week for the Gym/commons area. Concrete pours occurred over metal decking on the second half of the 2ndfloor and first half of the 3rd floor of the classroom building. Foundationand stem wall excavation and forming started in the administration area.Foundation and stem wall concrete pours completed at the band roomand outside play areas. Mechanical and Electrical equipment supports are being placed this weekin the Classroom building. Underground utilities are continuing on sitewith the side sewers to start this week

Hazel Wolf K-8 at PinehurstSite Plan

Hazel Wolf K-8 at PinehurstAerial View from the West

Hazel Wolf K-8 at PinehurstArea A1 Placing Metal DeckingSeptember 17, 2015

Hazel Wolf K-8 at PinehurstArea A2 2nd Floor Slab-on-DeckSeptember 15, 2015

Hazel Wolf K-8 at PinehurstArea A1 Final Footings and Stem WallsSeptember 16, 2015

Hazel Wolf K-8 at PinehurstArea A1 to Area C Steel Erection and FootingsSeptember 15, 2015

Hazel Wolf K-8 at PinehurstArea A2 Structural Steel CompleteSeptember 15, 2015

Hazel Wolf K-8 at PinehurstArea A2 3rd Floor First Half Concrete Slab PourSeptember 17, 2015

Hazel Wolf K-8 at PinehurstArea A3 Placing Rebar to FootingsSeptember 17, 2015

Hazel Wolf K-8 at PinehurstArea B Final FootingSeptember 15, 2015

New Thornton Creek Building Building A: Continued excavation of footings at northwest corner. Appliedwaterproofing to concrete footings and stem walls. Underground plumbingand electrical ongoing. Backfilled interior side of footings on east portion. Building B: Placed gravel capillary break, vapor barrier, steel mesh and rebarfor library concrete slab on grade. Began erecting steel at library. Completedunder ground electrical and plumbing for library. More structural steeldelivery for Building B. Building C: Steel erection completed with steel joist and decking. Light gaugeexterior metal stud framing continues. Site: Completed subgrade and excavation of rain garden for west parking lot.Began forming concrete curbs in west parking lot. Set light pole bases east ofBuilding C. Paved west parking lot. Began relocating construction trailers towest parking lot.

New Thornton Creek BuildingKey Plan

New Thornton Creek BuildingAerial PhotoSeptember 14, 2015

New Thornton Creek BuildingBuilding A Fine Grading for Slab-on-grade

New Thornton Creek BuildingBuilding A Waterproofing at Footings and Stem Walls

New Thornton Creek BuildingBuilding B Concrete Slab-on-Grade

New Thornton Creek BuildingBuilding B Placing Gravel Capillary Break for Library

New Thornton Creek BuildingBuilding B Vapor Barrier, Steel Mesh and Rebar

New Thornton Creek BuildingBuilding C Light Gauge Metal Stud Framing

New Thornton Creek BuildingPaving West Parking Lot

New Thornton Creek BuildingPaving West Parking Lot

Sep 25, 2015 · Arbor Heights Elementary School 2 Genesee Hill Elementary School 13 Hazel Wolf K-8 at Pinehurst 24 New Thornton Creek Building 35 September 25, 2015 Seattle Public Schools Building Excellence IV Projects Under Construction . Arbor Heights Elem